Find the sequence that minimizes total elapsed time to complete the following jobs in the order XY. Find the total elasped time and idle times for each machine.

Jobs A B C D E
Machine X 10 2 18 6 20
Machine Y 4 12 14 16 8
सारिणी
योग

उत्तर

Job A B C D E
Machine X 10 2 18 6 20
Machine Y 4 12 14 16 8

Observe that Min(X, Y) = 2, corresponding to job B on machine X.

∴ Job B is placed first in sequence

B        

Then the problem reduces to

Job A C D E
Machine X 10 18 6 20
Machine Y 4 14 16 8

Now, Min(X, Y) = 4, corresponds to job A on machine Y.

∴ Job A is placed last in sequence.

B       A

Then the problem reduces to

Job C D E
Machine X 18 6 20
Machine Y 14 16 8

Now, Min(X, Y) = 6, corresponds to job D on machine X.

∴ Job D is placed second in sequence.

B D     A

Then the problem reduces to

Job C E
Machine X 18 20
Machine Y 14 8

Now, Min(X, Y) = 8, corresponds to job E on machine Y.

∴ Job E is placed fourth and job C on remaining in sequence.

∴ The optimal sequence is

B D C E A

Total elapsed time,

Job Machine X Machine Y
In Out In Out
B (2, 12) 0 2 2 14
D (6, 16) 2 8 14 30
C (18, 14) 8 26 30 44
E (20, 8) 26 46 46 54
A (10, 4) 46 56 56 60

∴ Total elapsed time = 60 hrs.

Idle time for machine X = 60 – 56 = 4 hrs

Idle time for machine Y = 2 + 2 + 2 = 6 hrs

shaalaa.com
Types of Sequencing Problem
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 2.7: Assignment Problem and Sequencing - Q.4

संबंधित प्रश्न

A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.

Job 1 2 3 4 5 6
Time of turning 3 12 5 2 9 11
Time for threading 8 10 9 6 3 1

A company has three jobs on hand. Each of these must be processed through two departments, in the order AB where
Department A: Press shop and
Department B: Finishing
The table below gives the number of days required by each job in each department

Job I II III
Department A 8 6 5
Department B 8 3 4

Find the sequence in which the three jobs should be processed so as to take minimum time to finish all the three jobs. Also find idle time for both the departments.


An insurance company receives three types of policy application bundles daily from its head office for data entry and tiling. The time (in minutes) required for each type for these two operations is given in the following table:

Policy 1 2 3
Data Entry 90 120 180
Filing 140 110 100

Find the sequence that minimizes the total time required to complete the entire task.


There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.

Job A B C D E
Machine X 10 2 18 6 20
Machine Y 4 12 14 16 8

Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.

Job I II IIII IV V VI VII
Machine A 7 16 19 10 14 15 5
Machine B 12 14 14 10 16 5 7

Choose the correct alternative :

The objective of sequencing problem is


If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.


Fill in the blank :

The time for which a machine j does not have a job to process to the start of job is called _______.


Fill in the blank :

The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is _______


One machine - one job is not an assumption in solving sequencing problems.


State whether the following is True or False :

If there are two least processing times for machine A and machine B, priority is given for the processing time which has lowest time of the adjacent machine.


State whether the following is True or False :

The time involved in moving a job from one machine to another is negligibly small.


Solve the following problem :

A readymade garments manufacturer has to process 7 items through two stages of production, namely cutting and sewing. The time taken in hours for each of these items in different stages are given below:

Items 1 2 3 4 5 6 7
Time for Cutting 5 7 3 4 6 7 12
Time for Sewing 2 6 7 5 9 5 8

Find the sequence in which these items are to be processed through these stages so as to minimize the total processing time. Also find the idle time of each machine.


Solve the following problem :

Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.

Job I II III IV V
Lathe 4 1 5 2 5
Surface grinder 3 2 4 3 6

Solve the following problem :

Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in order AB.

Machines Jobs (Processing times in minutes)
I II III IV V VI VII
Machine A 12 6 5 11 5 7 6
Machine B 7 8 9 4 7 8 3

Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.


A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.

Type 1 2 3 4 5
Machine A 16 20 12 14 22
Machine B 10 12 4 6 8
Machine C 8 18 16 12 10

Solve the problem for minimizing the total elapsed time.


Solve the following problem :

A foreman wants to process 4 different jobs on three machines: a shaping machine, a drilling machine and a tapping machine, the sequence of operations being shaping-drilling-tapping. Decide the optimal sequence for the four jobs to minimize the total elapsed time. Also find the total elapsed time and the idle time for every machine.

Job Shaping (Minutes) Drilling (Minutes) Trapping (Minutes)
1 13 3 18
2 18 8 4
3 8 6 13
4 23 6 8

Choose the correct alternative:

If there are 3 machines A, B and C, conditions for reducing a 3 machine problem to a 2 machine problem with respect to minimum processing time is ______


If there are n jobs and m machines, then there will be _______ sequence of doing jobs.


Choose the correct alternative:

In solving 2 machine and n jobs sequencing problem, the following assumption is wrong


In sequencing problem the time required to transfer a job from one machine to another is ______


State whether the following statement is True or False:

The idle time for a machine is the when machine is available but is not waiting for any job to be processed


State whether the following statement is True or False: 

In sequencing problem each job once started on any machine must be processed still its completion


A publisher produces 5 books on Mathematics. The books have to go through composing, printing and binding done by 3 machines A, B, C. The time schedule for the entire task in proper unit is as follows :

Book I II III IV V
Machine A 4 9 8 6 5
Machine B 5 6 2 3 4
Machine C 8 10 6 7 11

Determine the optimum time required to finish the entire task. Also, find idle time for machines A, B, C.