हिंदी

Solve the following problem : A readymade garments manufacturer has to process 7 items through two stages of production, namely cutting and sewing. The time taken in hours for each of these - Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

Solve the following problem :

A readymade garments manufacturer has to process 7 items through two stages of production, namely cutting and sewing. The time taken in hours for each of these items in different stages are given below:

Items 1 2 3 4 5 6 7
Time for Cutting 5 7 3 4 6 7 12
Time for Sewing 2 6 7 5 9 5 8

Find the sequence in which these items are to be processed through these stages so as to minimize the total processing time. Also find the idle time of each machine.

योग

उत्तर

Items 1 2 3 4 5 6 7
Time for Cutting 5 7 3 4 6 7 12
Time for Sewing 2 6 7 5 9 5 8

Observe that Min (cutting, sewing) = 2, corresponds to item 1 on sewing.
∴ Item 1 is placed last in sequence.

            1

Then the problem reduces to

Items 2 3 4 5 6 7
Time for Cutting 7 3 4 6 7 12
Time for Sewing 6 7 5 9 5 8

Now, Min (cutting, sewing) = 3, corresponds to item 3 on cutting.
∴ Item 3 is placed first in sequence.

3           1

Then the problem reduces to

Items 2 4 5 6 7
Time for Cutting 7 4 6 7 12
Time for Sewing 6 5 9 5 8

Now, Min (cutting, sewing) = 4, corresponds to item 4 on cutting.
∴ Item 4 is placed after 3 in sequence.

3 4           1

Item 4 is placed after 3 in sequence.

Items 2 5 6 7
Time for Cutting 7 6 7 12
Time for Sewing 6 9 5 8

Now, Min (cutting, sewing) = 5, corresponds to item 6 on sewing
∴ Item 6 is placed before 1 in sequence.

3 4       6 1

Then the problem reduces to

Items 2 5 7
Time for Cutting 7 6 12
Time for Sewing 6 9 8

Now, Min (cutting, sewing) = 6, corresponds to item 2 on sewing and item 5 on cutting.
∴ Item 2 is placed before 6 and item 5 is placed after 4 and item 7 on remaining in sequence.
∴ Optimal sequence is

3 4 5 7 2 6 1

Total elapsed time

Item Cutting Sewing
In Out In Out
3 (3, 7) 0 3 3 10
4 (4, 5) 3 7 10 15
5 (6, 9) 7 13 15 24
7 (12, 8) 13 25 25 33
2 (7, 6) 25 32 33 39
6 (7, 5) 32 39 39 44
1 (5, 2) 39 44 44 46

∴ Total elapsed time = 46 hrs
Idle time for cutting = 46  44 = 2 hrs
Idle time for sewing = 3 + 1 = 4 hrs.

shaalaa.com
Types of Sequencing Problem
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 7: Assignment Problem and Sequencing - Part II [पृष्ठ १२९]

APPEARS IN

बालभारती Mathematics and Statistics 2 (Commerce) [English] 12 Standard HSC Maharashtra State Board
अध्याय 7 Assignment Problem and Sequencing
Part II | Q 1 | पृष्ठ १२९

संबंधित प्रश्न

A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.

Job 1 2 3 4 5 6
Time of turning 3 12 5 2 9 11
Time for threading 8 10 9 6 3 1

A company has three jobs on hand. Each of these must be processed through two departments, in the order AB where
Department A: Press shop and
Department B: Finishing
The table below gives the number of days required by each job in each department

Job I II III
Department A 8 6 5
Department B 8 3 4

Find the sequence in which the three jobs should be processed so as to take minimum time to finish all the three jobs. Also find idle time for both the departments.


There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.

Job A B C D E
Machine X 10 2 18 6 20
Machine Y 4 12 14 16 8

Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.

Job I II IIII IV V VI VII
Machine A 7 16 19 10 14 15 5
Machine B 12 14 14 10 16 5 7

If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.


Choose the correct alternative :

In a 3 machine and 5 jobs problem, the least of processing times on machine A, B and C are 5, 1 and 3 hours and the highest processing times are 9, 5 and 7 respectively, then it can be converted to a 2 machine problem if order of the machines is:


Fill in the blank :

The time for which a machine j does not have a job to process to the start of job is called _______.


Fill in the blank :

The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is _______


One machine - one job is not an assumption in solving sequencing problems.


State whether the following is True or False :

One of the assumptions made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine.


Solve the following problem :

Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in order AB.

Machines Jobs (Processing times in minutes)
I II III IV V VI VII
Machine A 12 6 5 11 5 7 6
Machine B 7 8 9 4 7 8 3

Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.


Solve the following problem :

A foreman wants to process 4 different jobs on three machines: a shaping machine, a drilling machine and a tapping machine, the sequence of operations being shaping-drilling-tapping. Decide the optimal sequence for the four jobs to minimize the total elapsed time. Also find the total elapsed time and the idle time for every machine.

Job Shaping (Minutes) Drilling (Minutes) Trapping (Minutes)
1 13 3 18
2 18 8 4
3 8 6 13
4 23 6 8

Choose the correct alternative:

If there are 3 machines A, B and C, conditions for reducing a 3 machine problem to a 2 machine problem with respect to minimum processing time is ______


______ time is the time when the machine is available but is waiting for a job to be processed


State whether the following statement is True or False:

The Total Elapsed is the time required to complete all the jobs i.e. entire task


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×