Advertisements
Advertisements
Question
Solve the following problem :
A readymade garments manufacturer has to process 7 items through two stages of production, namely cutting and sewing. The time taken in hours for each of these items in different stages are given below:
Items | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
Time for Cutting | 5 | 7 | 3 | 4 | 6 | 7 | 12 |
Time for Sewing | 2 | 6 | 7 | 5 | 9 | 5 | 8 |
Find the sequence in which these items are to be processed through these stages so as to minimize the total processing time. Also find the idle time of each machine.
Solution
Items | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
Time for Cutting | 5 | 7 | 3 | 4 | 6 | 7 | 12 |
Time for Sewing | 2 | 6 | 7 | 5 | 9 | 5 | 8 |
Observe that Min (cutting, sewing) = 2, corresponds to item 1 on sewing.
∴ Item 1 is placed last in sequence.
1 |
Then the problem reduces to
Items | 2 | 3 | 4 | 5 | 6 | 7 |
Time for Cutting | 7 | 3 | 4 | 6 | 7 | 12 |
Time for Sewing | 6 | 7 | 5 | 9 | 5 | 8 |
Now, Min (cutting, sewing) = 3, corresponds to item 3 on cutting.
∴ Item 3 is placed first in sequence.
3 | 1 |
Then the problem reduces to
Items | 2 | 4 | 5 | 6 | 7 |
Time for Cutting | 7 | 4 | 6 | 7 | 12 |
Time for Sewing | 6 | 5 | 9 | 5 | 8 |
Now, Min (cutting, sewing) = 4, corresponds to item 4 on cutting.
∴ Item 4 is placed after 3 in sequence.
3 | 4 | 1 |
Item 4 is placed after 3 in sequence.
Items | 2 | 5 | 6 | 7 |
Time for Cutting | 7 | 6 | 7 | 12 |
Time for Sewing | 6 | 9 | 5 | 8 |
Now, Min (cutting, sewing) = 5, corresponds to item 6 on sewing
∴ Item 6 is placed before 1 in sequence.
3 | 4 | 6 | 1 |
Then the problem reduces to
Items | 2 | 5 | 7 |
Time for Cutting | 7 | 6 | 12 |
Time for Sewing | 6 | 9 | 8 |
Now, Min (cutting, sewing) = 6, corresponds to item 2 on sewing and item 5 on cutting.
∴ Item 2 is placed before 6 and item 5 is placed after 4 and item 7 on remaining in sequence.
∴ Optimal sequence is
3 | 4 | 5 | 7 | 2 | 6 | 1 |
Total elapsed time
Item | Cutting | Sewing | ||
In | Out | In | Out | |
3 (3, 7) | 0 | 3 | 3 | 10 |
4 (4, 5) | 3 | 7 | 10 | 15 |
5 (6, 9) | 7 | 13 | 15 | 24 |
7 (12, 8) | 13 | 25 | 25 | 33 |
2 (7, 6) | 25 | 32 | 33 | 39 |
6 (7, 5) | 32 | 39 | 39 | 44 |
1 (5, 2) | 39 | 44 | 44 | 46 |
∴ Total elapsed time = 46 hrs
Idle time for cutting = 46 44 = 2 hrs
Idle time for sewing = 3 + 1 = 4 hrs.
APPEARS IN
RELATED QUESTIONS
A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.
Job | 1 | 2 | 3 | 4 | 5 | 6 |
Time of turning | 3 | 12 | 5 | 2 | 9 | 11 |
Time for threading | 8 | 10 | 9 | 6 | 3 | 1 |
A company has three jobs on hand. Each of these must be processed through two departments, in the order AB where
Department A: Press shop and
Department B: Finishing
The table below gives the number of days required by each job in each department
Job | I | II | III |
Department A | 8 | 6 | 5 |
Department B | 8 | 3 | 4 |
Find the sequence in which the three jobs should be processed so as to take minimum time to finish all the three jobs. Also find idle time for both the departments.
Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.
Job | I | II | IIII | IV | V | VI | VII |
Machine A | 7 | 16 | 19 | 10 | 14 | 15 | 5 |
Machine B | 12 | 14 | 14 | 10 | 16 | 5 | 7 |
Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hours.
Jobs | I | II | III | IV | V | VI | VII |
Machine A | 6 | 7 | 5 | 11 | 6 | 7 | 12 |
Machine B | 4 | 3 | 2 | 5 | 1 | 5 | 3 |
Machine C | 3 | 8 | 7 | 4 | 9 | 8 | 7 |
Choose the correct alternative :
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
Choose the correct alternative :
In a 3 machine and 5 jobs problem, the least of processing times on machine A, B and C are 5, 1 and 3 hours and the highest processing times are 9, 5 and 7 respectively, then it can be converted to a 2 machine problem if order of the machines is:
Fill in the blank :
The time for which a machine j does not have a job to process to the start of job is called _______.
State whether the following is True or False :
If there are two least processing times for machine A and machine B, priority is given for the processing time which has lowest time of the adjacent machine.
State whether the following is True or False :
One of the assumptions made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine.
State whether the following is True or False :
In a sequencing problem, a machine can process more than one job at a time.
State whether the following is True or False :
The time involved in moving a job from one machine to another is negligibly small.
Choose the correct alternative:
Machine | Job | |||
A | B | C | D | |
I | 5 | 6 | 8 | 4 |
II | 4 | 7 | 9 | 10 |
The optimal sequence for above data is
In sequencing problem the time required to transfer a job from one machine to another is ______
State whether the following statement is True or False:
The Total Elapsed is the time required to complete all the jobs i.e. entire task
The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______
A publisher produces 5 books on Mathematics. The books have to go through composing, printing and binding done by 3 machines A, B, C. The time schedule for the entire task in proper unit is as follows :
Book | I | II | III | IV | V |
Machine A | 4 | 9 | 8 | 6 | 5 |
Machine B | 5 | 6 | 2 | 3 | 4 |
Machine C | 8 | 10 | 6 | 7 | 11 |
Determine the optimum time required to finish the entire task. Also, find idle time for machines A, B, C.