Advertisements
Advertisements
Question
A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.
Job | 1 | 2 | 3 | 4 | 5 | 6 |
Time of turning | 3 | 12 | 5 | 2 | 9 | 11 |
Time for threading | 8 | 10 | 9 | 6 | 3 | 1 |
Solution
Job | 1 | 2 | 3 | 4 | 5 | 6 |
Time of turning | 3 | 12 | 5 | 2 | 9 | 11 |
Time for threading | 8 | 10 | 9 | 6 | 3 | 1 |
Observe that Min (turning, threading) = 1, which corresponds to job 6 on threading machine.
Therefore, job 6 is placed last in sequence.
6 |
Then the problem reduces to
Job | 1 | 2 | 3 | 4 | 5 |
Time of turning | 3 | 12 | 5 | 2 | 9 |
Time for threading | 8 | 10 | 9 | 6 | 3 |
Now, Min (turning, threading) = 2, which corresponds to job 4 on turning machine
∴ Job 4 is placed first in sequence.
4 | 6 |
Then the problem reduces to
Job | 1 | 2 | 3 | 5 |
Time of turning | 3 | 12 | 5 | 9 |
Time for threading | 8 | 10 | 9 | 3 |
Now, Min (turning, threading) = 3, which corresponds to job 1 on turning and job 5 on threading.
∴ Job 1 is placed second and job 5 is placed second last.
4 | 1 | 5 | 6 |
Then the problem reduces to
Job | 2 | 3 |
Time of turning | 12 | 5 |
Time for threading | 10 | 9 |
Now, Min (turning, threading) = 5, which corresponds to job 3 on turning.
∴ Job 3 is placed third on sequence and job 2 on remaining.
∴ Optimal solution is
4 | 1 | 3 | 2 | 5 | 6 |
Total elapsed time
Job | Turning | Threading | ||
In | Out | In | Out | |
4(2, 6) | 0 | 2 | 2 | 8 |
1(3, 8) | 2 | 5 | 8 | 16 |
3(5, 9) | 5 | 10 | 16 | 25 |
2(12, 10) | 10 | 22 | 25 | 35 |
5(9, 3) | 22 | 31 | 35 | 38 |
6(11, 1) | 31 | 42 | 42 | 43 |
∴ Total elapsed time = 43 mins
Idle time for turning = 43 – 42 = 1 min
Idle time for threading = 2 + 4 = 6 mins.
APPEARS IN
RELATED QUESTIONS
Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hours.
Jobs | I | II | III | IV | V | VI | VII |
Machine A | 6 | 7 | 5 | 11 | 6 | 7 | 12 |
Machine B | 4 | 3 | 2 | 5 | 1 | 5 | 3 |
Machine C | 3 | 8 | 7 | 4 | 9 | 8 | 7 |
If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.
Choose the correct alternative :
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
Fill in the blank :
The time for which a machine j does not have a job to process to the start of job is called _______.
State whether the following is True or False :
In a sequencing problem, the processing times are dependent of order of processing the jobs on machines.
State whether the following is True or False :
One of the assumptions made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine.
State whether the following is True or False :
In a sequencing problem, a machine can process more than one job at a time.
State whether the following is True or False :
The time involved in moving a job from one machine to another is negligibly small.
Solve the following problem :
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.
Job | I | II | III | IV | V |
Lathe | 4 | 1 | 5 | 2 | 5 |
Surface grinder | 3 | 2 | 4 | 3 | 6 |
A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.
Type | 1 | 2 | 3 | 4 | 5 |
Machine A | 16 | 20 | 12 | 14 | 22 |
Machine B | 10 | 12 | 4 | 6 | 8 |
Machine C | 8 | 18 | 16 | 12 | 10 |
Solve the problem for minimizing the total elapsed time.
Choose the correct alternative:
Machine | Job | |||
A | B | C | D | |
I | 5 | 6 | 8 | 4 |
II | 4 | 7 | 9 | 10 |
The optimal sequence for above data is
Choose the correct alternative:
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
In sequencing problem the time required to transfer a job from one machine to another is ______
State whether the following statement is True or False:
In sequencing problem each job once started on any machine must be processed still its completion
State whether the following statement is True or False:
In sequencing problem each machine is of different type
Find the sequence that minimizes total elapsed time to complete the following jobs in the order XY. Find the total elasped time and idle times for each machine.
Jobs | A | B | C | D | E |
Machine X | 10 | 2 | 18 | 6 | 20 |
Machine Y | 4 | 12 | 14 | 16 | 8 |
The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______