A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. - Mathematics and Statistics

Advertisements
Advertisements

Questions

A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.

Type 1 2 3 4 5
Machine A 16 20 12 14 22
Machine B 10 12 4 6 8
Machine C 8 18 16 12 10

Solve the problem for minimizing the total elapsed time.

A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.

Type 1 2 3 4 5
Machine A 16 20 12 14 22
Machine B 10 12 4 6 8
Machine C 8 18 16 12 10

Find the total elapsed time and also find idle time for machine B.

Chart
Sum

Solution

Type 1 2 3 4 5
Machine A 16 20 12 14 22
Machine B 10 12 4 6 8
Machine C 8 18 16 12 10

Here min A = 12, max B = 12, min C = 8.

Since min A ≥ max B is satisfied, the problem can be converted into a two-machine problem.

Let G and H be two fictitious machines such that G = A + B and H = B + C

Then the problem can be written as

Type 1 2 3 4 5
Machine G 26 32 16 20 30
Machine H 18 30 20 18 18

Using the optimal sequence algorithm, any one is an optimal sequence that can be obtained.

  3 2 5 4 1
or 3 2 5 1 4
or 3 2 4 5 1
or 3 2 4 1 5
or 3 2 1 4 5
or 3 2 1 5 4

 

Type Machine A Machine B Machine C
3 0 12 12 16 16 32
2 12 32 32 44 44 62
5 32 54 54 62 62 72
4 54 68 68 74 74 86
1 68 84 84 94 94 102

∴ Total elapsed time = 102 hrs.

Idle time for machine A = 102 – 84 = 18 hrs

Idle time for machine B = (102 – 94) + 54 = 62 hrs

Idle time for machine C = 16 + 12 + 2 + 8 = 38 hrs.

shaalaa.com

Notes

Students can refer to the provided solution According to their question.

Types of Sequencing Problem
  Is there an error in this question or solution?
Chapter 7: Assignment Problem and Sequencing - Part II [Page 129]

RELATED QUESTIONS

A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.

Job 1 2 3 4 5 6
Time of turning 3 12 5 2 9 11
Time for threading 8 10 9 6 3 1

A company has three jobs on hand. Each of these must be processed through two departments, in the order AB where
Department A: Press shop and
Department B: Finishing
The table below gives the number of days required by each job in each department

Job I II III
Department A 8 6 5
Department B 8 3 4

Find the sequence in which the three jobs should be processed so as to take minimum time to finish all the three jobs. Also find idle time for both the departments.


An insurance company receives three types of policy application bundles daily from its head office for data entry and tiling. The time (in minutes) required for each type for these two operations is given in the following table:

Policy 1 2 3
Data Entry 90 120 180
Filing 140 110 100

Find the sequence that minimizes the total time required to complete the entire task.


There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.

Job A B C D E
Machine X 10 2 18 6 20
Machine Y 4 12 14 16 8

Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.

Job I II IIII IV V VI VII
Machine A 7 16 19 10 14 15 5
Machine B 12 14 14 10 16 5 7

If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.


Choose the correct alternative :

In solving 2 machine and n jobs sequencing problem, the following assumption is wrong


Fill in the blank :

The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is _______


One machine - one job is not an assumption in solving sequencing problems.


State whether the following is True or False :

In a sequencing problem, a machine can process more than one job at a time.


Solve the following problem :

A readymade garments manufacturer has to process 7 items through two stages of production, namely cutting and sewing. The time taken in hours for each of these items in different stages are given below:

Items 1 2 3 4 5 6 7
Time for Cutting 5 7 3 4 6 7 12
Time for Sewing 2 6 7 5 9 5 8

Find the sequence in which these items are to be processed through these stages so as to minimize the total processing time. Also find the idle time of each machine.


Solve the following problem :

Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.

Job I II III IV V
Lathe 4 1 5 2 5
Surface grinder 3 2 4 3 6

Choose the correct alternative:

If there are 3 machines A, B and C, conditions for reducing a 3 machine problem to a 2 machine problem with respect to minimum processing time is ______


In assignment problem each worker or machine is ______ capable of handling any job


______ time is the time when the machine is available but is waiting for a job to be processed


State whether the following statement is True or False: 

One of the assumptions is made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine


State whether the following statement is True or False:

The Total Elapsed is the time required to complete all the jobs i.e. entire task


State whether the following statement is True or False:

The idle time for a machine is the when machine is available but is not waiting for any job to be processed


State whether the following statement is True or False: 

In sequencing problem each job once started on any machine must be processed still its completion


State whether the following statement is True or False:

In sequencing problem each machine is of different type


The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______