Advertisements
Advertisements
Question
Solve the following problem :
Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in order AB.
Machines | Jobs (Processing times in minutes) | ||||||
I | II | III | IV | V | VI | VII | |
Machine A | 12 | 6 | 5 | 11 | 5 | 7 | 6 |
Machine B | 7 | 8 | 9 | 4 | 7 | 8 | 3 |
Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle times for both the machines.
Solution
Machines | Jobs (Processing times in minutes) | ||||||
I | II | III | IV | V | VI | VII | |
Machine A | 12 | 6 | 5 | 11 | 5 | 7 | 6 |
Machine B | 7 | 8 | 9 | 4 | 7 | 8 | 3 |
Observe that Min (A, B) = 3, corresponds to job VII on machine B.
∴ Job VII is placed last in sequence.
VII |
Then the problem reduces to
Machines | Jobs (Processing times in minutes) | |||||
I | II | III | IV | V | VI | |
Machine A | 12 | 6 | 5 | 11 | 5 | 7 |
Machine B | 7 | 8 | 9 | 4 | 7 | 8 |
Now, Min (A, B) = 4, corresponds to job IV on machine B
∴ Job IV is placed before VII in sequence.
IV | VII |
Then the problem reduces to
Machines | Jobs (Processing times in minutes) | ||||
I | II | III | V | VI | |
Machine A | 12 | 6 | 5 | 5 | 7 |
Machine B | 7 | 8 | 9 | 7 | 8 |
Now, Min (A, B) = 5, corresponds to job III and V on machine A.
∴ Job III and V is placed either first or second in sequence.
III | V | IV | VII |
OR |
V | III | IV | VII |
Then the problem reduces to
Machines | Jobs (Processing times in minutes) | ||
I | II | VI | |
Machine A | 12 | 6 | 7 |
Machine B | 7 | 8 | 8 |
Now, Min (A, B) = 6, corresponds to job II on machine A
∴ Job II is placed on third place in sequence.
III | V | II | IV | VII |
OR |
V | III | II | IV | VII |
Then the problem reduces to
Machines | Jobs (Processing times in minutes) | |
I | VI | |
Machine A | 12 | 7 |
Machine B | 7 | 8 |
Now, Min (A, B) = 7, corresponds to job I on machine B and VI on machine A.
∴ Job I is placed before IV and job VI on remaining in sequence.
III | V | II | VI | I | IV | VII |
OR |
V | III | II | VI | I | IV | VII |
We take the optimal sequence as,
III | V | II | VI | I | IV | VII |
Total elapsed time
Job | Machine A | Machine B | ||
In | Out | In | Out | |
III (5, 9) | 0 | 5 | 5 | 14 |
V (5, 7) | 5 | 10 | 14 | 21 |
II (6, 8) | 10 | 16 | 21 | 29 |
VI (7, 8) | 16 | 23 | 29 | 37 |
I (12, 7) | 23 | 35 | 37 | 44 |
IV (11, 4) | 35 | 46 | 46 | 50 |
VII (6, 3) | 46 | 52 | 52 | 55 |
∴ Total elapsed time = 55 mins
Idle time for machine A = 55 – 52 = 3 mins
Idle time for machine B = 5 + 2 + 2 = 9 mins.
APPEARS IN
RELATED QUESTIONS
A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.
Job | 1 | 2 | 3 | 4 | 5 | 6 |
Time of turning | 3 | 12 | 5 | 2 | 9 | 11 |
Time for threading | 8 | 10 | 9 | 6 | 3 | 1 |
A company has three jobs on hand. Each of these must be processed through two departments, in the order AB where
Department A: Press shop and
Department B: Finishing
The table below gives the number of days required by each job in each department
Job | I | II | III |
Department A | 8 | 6 | 5 |
Department B | 8 | 3 | 4 |
Find the sequence in which the three jobs should be processed so as to take minimum time to finish all the three jobs. Also find idle time for both the departments.
An insurance company receives three types of policy application bundles daily from its head office for data entry and tiling. The time (in minutes) required for each type for these two operations is given in the following table:
Policy | 1 | 2 | 3 |
Data Entry | 90 | 120 | 180 |
Filing | 140 | 110 | 100 |
Find the sequence that minimizes the total time required to complete the entire task.
There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.
Job | A | B | C | D | E |
Machine X | 10 | 2 | 18 | 6 | 20 |
Machine Y | 4 | 12 | 14 | 16 | 8 |
Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.
Job | I | II | IIII | IV | V | VI | VII |
Machine A | 7 | 16 | 19 | 10 | 14 | 15 | 5 |
Machine B | 12 | 14 | 14 | 10 | 16 | 5 | 7 |
Choose the correct alternative :
The objective of sequencing problem is
Choose the correct alternative :
In a 3 machine and 5 jobs problem, the least of processing times on machine A, B and C are 5, 1 and 3 hours and the highest processing times are 9, 5 and 7 respectively, then it can be converted to a 2 machine problem if order of the machines is:
Fill in the blank :
The time for which a machine j does not have a job to process to the start of job is called _______.
Fill in the blank :
The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is _______
One machine - one job is not an assumption in solving sequencing problems.
State whether the following is True or False :
One of the assumptions made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine.
Solve the following problem :
A readymade garments manufacturer has to process 7 items through two stages of production, namely cutting and sewing. The time taken in hours for each of these items in different stages are given below:
Items | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
Time for Cutting | 5 | 7 | 3 | 4 | 6 | 7 | 12 |
Time for Sewing | 2 | 6 | 7 | 5 | 9 | 5 | 8 |
Find the sequence in which these items are to be processed through these stages so as to minimize the total processing time. Also find the idle time of each machine.
Solve the following problem :
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.
Job | I | II | III | IV | V |
Lathe | 4 | 1 | 5 | 2 | 5 |
Surface grinder | 3 | 2 | 4 | 3 | 6 |
Choose the correct alternative:
If there are 3 machines A, B and C, conditions for reducing a 3 machine problem to a 2 machine problem with respect to minimum processing time is ______
______ time is the time when the machine is available but is waiting for a job to be processed
State whether the following statement is True or False:
The Total Elapsed is the time required to complete all the jobs i.e. entire task
State whether the following statement is True or False:
In sequencing problem each job once started on any machine must be processed still its completion
Find the sequence that minimizes total elapsed time to complete the following jobs in the order XY. Find the total elasped time and idle times for each machine.
Jobs | A | B | C | D | E |
Machine X | 10 | 2 | 18 | 6 | 20 |
Machine Y | 4 | 12 | 14 | 16 | 8 |
The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______
A publisher produces 5 books on Mathematics. The books have to go through composing, printing and binding done by 3 machines A, B, C. The time schedule for the entire task in proper unit is as follows :
Book | I | II | III | IV | V |
Machine A | 4 | 9 | 8 | 6 | 5 |
Machine B | 5 | 6 | 2 | 3 | 4 |
Machine C | 8 | 10 | 6 | 7 | 11 |
Determine the optimum time required to finish the entire task. Also, find idle time for machines A, B, C.