Choose the correct alternative : In a 3 machine and 5 jobs problem, the least of processing times on machine A, B and C are 5, 1 and 3 hours and the highest processing times are 9, 5 and 7 respective - Mathematics and Statistics

Advertisements
Advertisements

Question

Choose the correct alternative :

In a 3 machine and 5 jobs problem, the least of processing times on machine A, B and C are 5, 1 and 3 hours and the highest processing times are 9, 5 and 7 respectively, then it can be converted to a 2 machine problem if order of the machines is:

Options

  • B - A - C

  • A - B - C

  • C - B - A

  • Any Order

MCQ

Solution

A - B - C

shaalaa.com
Types of Sequencing Problem
  Is there an error in this question or solution?
Chapter 7: Assignment Problem and Sequencing - Miscellaneous Exercise 7 [Page 127]

APPEARS IN

Balbharati Mathematics and Statistics 2 (Commerce) [English] 12 Standard HSC Maharashtra State Board
Chapter 7 Assignment Problem and Sequencing
Miscellaneous Exercise 7 | Q 1.13 | Page 127

RELATED QUESTIONS

A company has three jobs on hand. Each of these must be processed through two departments, in the order AB where
Department A: Press shop and
Department B: Finishing
The table below gives the number of days required by each job in each department

Job I II III
Department A 8 6 5
Department B 8 3 4

Find the sequence in which the three jobs should be processed so as to take minimum time to finish all the three jobs. Also find idle time for both the departments.


Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.

Job I II IIII IV V VI VII
Machine A 7 16 19 10 14 15 5
Machine B 12 14 14 10 16 5 7

If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.


Choose the correct alternative :

In solving 2 machine and n jobs sequencing problem, the following assumption is wrong


One machine - one job is not an assumption in solving sequencing problems.


State whether the following is True or False :

In a sequencing problem, a machine can process more than one job at a time.


State whether the following is True or False :

The time involved in moving a job from one machine to another is negligibly small.


Solve the following problem :

Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.

Job I II III IV V
Lathe 4 1 5 2 5
Surface grinder 3 2 4 3 6

A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.

Type 1 2 3 4 5
Machine A 16 20 12 14 22
Machine B 10 12 4 6 8
Machine C 8 18 16 12 10

Solve the problem for minimizing the total elapsed time.


Choose the correct alternative:

If there are 3 machines A, B and C, conditions for reducing a 3 machine problem to a 2 machine problem with respect to minimum processing time is ______


Choose the correct alternative:

In solving 2 machine and n jobs sequencing problem, the following assumption is wrong


______ time is the time when the machine is available but is waiting for a job to be processed


In sequencing problem the time required to transfer a job from one machine to another is ______


State whether the following statement is True or False: 

One of the assumptions is made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine


State whether the following statement is True or False:

In sequencing problem each machine is of different type


Find the sequence that minimizes total elapsed time to complete the following jobs in the order XY. Find the total elasped time and idle times for each machine.

Jobs A B C D E
Machine X 10 2 18 6 20
Machine Y 4 12 14 16 8

The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______