One of the assumptions made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine.
Options
True
False
Solution
One of the assumptions made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine False.
APPEARS IN
RELATED QUESTIONS
A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.
Job | 1 | 2 | 3 | 4 | 5 | 6 |
Time of turning | 3 | 12 | 5 | 2 | 9 | 11 |
Time for threading | 8 | 10 | 9 | 6 | 3 | 1 |
A company has three jobs on hand. Each of these must be processed through two departments, in the order AB where
Department A: Press shop and
Department B: Finishing
The table below gives the number of days required by each job in each department
Job | I | II | III |
Department A | 8 | 6 | 5 |
Department B | 8 | 3 | 4 |
Find the sequence in which the three jobs should be processed so as to take minimum time to finish all the three jobs. Also find idle time for both the departments.
An insurance company receives three types of policy application bundles daily from its head office for data entry and tiling. The time (in minutes) required for each type for these two operations is given in the following table:
Policy | 1 | 2 | 3 |
Data Entry | 90 | 120 | 180 |
Filing | 140 | 110 | 100 |
Find the sequence that minimizes the total time required to complete the entire task.
There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.
Job | A | B | C | D | E |
Machine X | 10 | 2 | 18 | 6 | 20 |
Machine Y | 4 | 12 | 14 | 16 | 8 |
One machine - one job is not an assumption in solving sequencing problems.
State whether the following is True or False :
If there are two least processing times for machine A and machine B, priority is given for the processing time which has lowest time of the adjacent machine.
State whether the following is True or False :
In a sequencing problem, the processing times are dependent of order of processing the jobs on machines.
State whether the following is True or False :
In a sequencing problem, a machine can process more than one job at a time.
Solve the following problem :
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.
Job | I | II | III | IV | V |
Lathe | 4 | 1 | 5 | 2 | 5 |
Surface grinder | 3 | 2 | 4 | 3 | 6 |
A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.
Type | 1 | 2 | 3 | 4 | 5 |
Machine A | 16 | 20 | 12 | 14 | 22 |
Machine B | 10 | 12 | 4 | 6 | 8 |
Machine C | 8 | 18 | 16 | 12 | 10 |
Solve the problem for minimizing the total elapsed time.
Choose the correct alternative:
Machine | Job | |||
A | B | C | D | |
I | 5 | 6 | 8 | 4 |
II | 4 | 7 | 9 | 10 |
The optimal sequence for above data is
Choose the correct alternative:
If there are 3 machines A, B and C, conditions for reducing a 3 machine problem to a 2 machine problem with respect to minimum processing time is ______
Choose the correct alternative:
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
In sequencing problem the time required to transfer a job from one machine to another is ______
State whether the following statement is True or False:
One of the assumptions is made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine
State whether the following statement is True or False:
The Total Elapsed is the time required to complete all the jobs i.e. entire task
State whether the following statement is True or False:
In sequencing problem each job once started on any machine must be processed still its completion