Advertisements
Advertisements
Questions
Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hours.
Jobs | I | II | III | IV | V | VI | VII |
Machine A | 6 | 7 | 5 | 11 | 6 | 7 | 12 |
Machine B | 4 | 3 | 2 | 5 | 1 | 5 | 3 |
Machine C | 3 | 8 | 7 | 4 | 9 | 8 | 7 |
Find the appropriate regression equation and use it to estimate the blood pressure of a woman with age 47 years. Find the optimal sequence that minimizes total time required to complete the following jobs in order A-B-C. The processing times are given in hrs.
Job | I | II | III | IV | V | VI | VII |
Machine A | 6 | 7 | 5 | 11 | 6 | 7 | 12 |
Machine B | 4 | 3 | 2 | 5 | 1 | 5 | 3 |
Machine C | 3 | 8 | 7 | 4 | 9 | 8 | 7 |
Solution
Job | I | II | III | IV | V | VI | VII |
Machine A | 6 | 7 | 5 | 11 | 6 | 7 | 12 |
Machine B | 4 | 3 | 2 | 5 | 1 | 5 | 3 |
Machine C | 3 | 8 | 7 | 4 | 9 | 8 | 7 |
Here min A = 5, max B = 5, min C = 3
Since min A ≥ max B is satisfied, the problem can be converted into a two machine problem.
Let G and H be two fictitious machines such that G = A + B and H = B + C
Then the problem can be written as
Job | I | II | III | IV | V | VI | VII |
Machine G | 10 | 10 | 7 | 16 | 7 | 12 | 15 |
Machine H | 7 | 11 | 9 | 9 | 10 | 13 | 10 |
Observe that Min (G, H) = 7, corresponds to job I on machine H, job III on machine G and job V on machine G.
∴ Job I is placed last in sequence, Job III and V are placed either first or second in sequence.
V | III | I |
OR |
III | V | I |
Then the problem reduces to
Job | II | IV | VI | VII |
Machine G | 10 | 16 | 12 | 15 |
Machine H | 11 | 9 | 13 | 10 |
Now, Min (G, H) = 9, corresponds to Job IV on machine H.
∴ Job IV is placed second last in the sequence.
V | III | IV | I |
OR |
III | V | IV | I |
Then the problem reduces to
Job | II | VI | VII |
Machine G | 10 | 12 | 15 |
Machine H | 11 | 13 | 10 |
Now, Min (G, H) = 10, corresponds to Job II on machine G and Job VII on machine H.
∴ Job II is placed third in the sequence, Job VII is placed third last in the sequence and remaining Job VI is placed fourth in the sequence.
V | III | II | VI | VII | IV | I |
OR |
III | V | II | VI | VII | IV | I |
∴ We consider the optimal sequence as V – III – II – VI – VII – IV – I
Total elapsed time
Job | Machine A |
Machine B |
Machine C |
|||
In | Out | In | Out | In | Out | |
V (6, 1, 9) | 0 | 6 | 6 | 7 | 7 | 16 |
III (5, 2, 7) | 6 | 11 | 11 | 13 | 16 | 23 |
II (7, 3, 8) | 11 | 18 | 18 | 21 | 23 | 31 |
VI (7, 5, 8) | 18 | 25 | 25 | 30 | 31 | 39 |
VII (12, 3, 7) | 25 | 37 | 37 | 40 | 40 | 47 |
IV (11, 5, 4) | 37 | 48 | 48 | 53 | 53 | 57 |
I (6, 4, 3) | 48 | 54 | 54 | 58 | 58 | 61 |
Total elapsed time = 61 hrs
Idle time for Machine A = 61 – 54 = 7 hrs
Idle time for Machine B = (61 – 58) + 6 + 4 + 5 + 4 + 7 + 8 + 1 = 38 hrs
Idle time for Machine C = 7 + 1 + 6 + 1 = 15 hrs.
APPEARS IN
RELATED QUESTIONS
A machine operator has to perform two operations, turning and threading on 6 different jobs. The time required to perform these operations (in minutes) for each job is known. Determine the order in which the jobs should be processed in order to minimize the total time required to complete all the jobs. Also find the total processing time and idle times for turning and threading operations.
Job | 1 | 2 | 3 | 4 | 5 | 6 |
Time of turning | 3 | 12 | 5 | 2 | 9 | 11 |
Time for threading | 8 | 10 | 9 | 6 | 3 | 1 |
An insurance company receives three types of policy application bundles daily from its head office for data entry and tiling. The time (in minutes) required for each type for these two operations is given in the following table:
Policy | 1 | 2 | 3 |
Data Entry | 90 | 120 | 180 |
Filing | 140 | 110 | 100 |
Find the sequence that minimizes the total time required to complete the entire task.
There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.
Job | A | B | C | D | E |
Machine X | 10 | 2 | 18 | 6 | 20 |
Machine Y | 4 | 12 | 14 | 16 | 8 |
Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.
Job | I | II | IIII | IV | V | VI | VII |
Machine A | 7 | 16 | 19 | 10 | 14 | 15 | 5 |
Machine B | 12 | 14 | 14 | 10 | 16 | 5 | 7 |
Choose the correct alternative :
The objective of sequencing problem is
If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.
Choose the correct alternative :
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
Choose the correct alternative :
In a 3 machine and 5 jobs problem, the least of processing times on machine A, B and C are 5, 1 and 3 hours and the highest processing times are 9, 5 and 7 respectively, then it can be converted to a 2 machine problem if order of the machines is:
Fill in the blank :
The time for which a machine j does not have a job to process to the start of job is called _______.
Fill in the blank :
The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is _______
State whether the following is True or False :
In a sequencing problem, a machine can process more than one job at a time.
Solve the following problem :
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.
Job | I | II | III | IV | V |
Lathe | 4 | 1 | 5 | 2 | 5 |
Surface grinder | 3 | 2 | 4 | 3 | 6 |
A toy manufacturing company produces five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.
Type | 1 | 2 | 3 | 4 | 5 |
Machine A | 16 | 20 | 12 | 14 | 22 |
Machine B | 10 | 12 | 4 | 6 | 8 |
Machine C | 8 | 18 | 16 | 12 | 10 |
Solve the problem for minimizing the total elapsed time.
Choose the correct alternative:
Machine | Job | |||
A | B | C | D | |
I | 5 | 6 | 8 | 4 |
II | 4 | 7 | 9 | 10 |
The optimal sequence for above data is
If there are n jobs and m machines, then there will be _______ sequence of doing jobs.
Choose the correct alternative:
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
In assignment problem each worker or machine is ______ capable of handling any job
______ time is the time when the machine is available but is waiting for a job to be processed
State whether the following statement is True or False:
The Total Elapsed is the time required to complete all the jobs i.e. entire task
State whether the following statement is True or False:
The idle time for a machine is the when machine is available but is not waiting for any job to be processed
State whether the following statement is True or False:
In sequencing problem each job once started on any machine must be processed still its completion
State whether the following statement is True or False:
In sequencing problem each machine is of different type
Find the sequence that minimizes total elapsed time to complete the following jobs in the order XY. Find the total elasped time and idle times for each machine.
Jobs | A | B | C | D | E |
Machine X | 10 | 2 | 18 | 6 | 20 |
Machine Y | 4 | 12 | 14 | 16 | 8 |
A publisher produces 5 books on Mathematics. The books have to go through composing, printing and binding done by 3 machines A, B, C. The time schedule for the entire task in proper unit is as follows :
Book | I | II | III | IV | V |
Machine A | 4 | 9 | 8 | 6 | 5 |
Machine B | 5 | 6 | 2 | 3 | 4 |
Machine C | 8 | 10 | 6 | 7 | 11 |
Determine the optimum time required to finish the entire task. Also, find idle time for machines A, B, C.