Advertisements
Advertisements
प्रश्न
Choose the correct alternative:
Machine | Job | |||
A | B | C | D | |
I | 5 | 6 | 8 | 4 |
II | 4 | 7 | 9 | 10 |
The optimal sequence for above data is
विकल्प
CDBA
DBCA
BCDA
ABCD
उत्तर
DBCA
APPEARS IN
संबंधित प्रश्न
A company has three jobs on hand. Each of these must be processed through two departments, in the order AB where
Department A: Press shop and
Department B: Finishing
The table below gives the number of days required by each job in each department
Job | I | II | III |
Department A | 8 | 6 | 5 |
Department B | 8 | 3 | 4 |
Find the sequence in which the three jobs should be processed so as to take minimum time to finish all the three jobs. Also find idle time for both the departments.
An insurance company receives three types of policy application bundles daily from its head office for data entry and tiling. The time (in minutes) required for each type for these two operations is given in the following table:
Policy | 1 | 2 | 3 |
Data Entry | 90 | 120 | 180 |
Filing | 140 | 110 | 100 |
Find the sequence that minimizes the total time required to complete the entire task.
There are five jobs, each of which must go through two machines in the order XY. Processing times (in hours) are given below. Determine the sequence for the jobs that will minimize the total elapsed time. Also find the total elapsed time and idle time for each machine.
Job | A | B | C | D | E |
Machine X | 10 | 2 | 18 | 6 | 20 |
Machine Y | 4 | 12 | 14 | 16 | 8 |
Find the optimal sequence that minimizes total time required to complete the following jobs in the order ABC. The processing times are given in hours.
Jobs | I | II | III | IV | V | VI | VII |
Machine A | 6 | 7 | 5 | 11 | 6 | 7 | 12 |
Machine B | 4 | 3 | 2 | 5 | 1 | 5 | 3 |
Machine C | 3 | 8 | 7 | 4 | 9 | 8 | 7 |
Choose the correct alternative :
The objective of sequencing problem is
If there are n jobs and m machines, then there will be_______ sequences of doing the jobs.
Fill in the blank :
The time for which a machine j does not have a job to process to the start of job is called _______.
Fill in the blank :
The time required for printing of four books A, B, C and D is 5, 8, 10 and 7 hours while its data entry requires 7, 4, 3 and 6 hrs respectively. The sequence that minimizes total elapsed time is _______
State whether the following is True or False :
In a sequencing problem, the processing times are dependent of order of processing the jobs on machines.
State whether the following is True or False :
One of the assumptions made while sequencing n jobs on 2 machines is: two jobs must be loaded at a time on any machine.
Solve the following problem :
A readymade garments manufacturer has to process 7 items through two stages of production, namely cutting and sewing. The time taken in hours for each of these items in different stages are given below:
Items | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
Time for Cutting | 5 | 7 | 3 | 4 | 6 | 7 | 12 |
Time for Sewing | 2 | 6 | 7 | 5 | 9 | 5 | 8 |
Find the sequence in which these items are to be processed through these stages so as to minimize the total processing time. Also find the idle time of each machine.
Solve the following problem :
Five jobs must pass through a lathe and a surface grinder, in that order. The processing times in hours are shown below. Determine the optimal sequence of the jobs. Also find the idle time of each machine.
Job | I | II | III | IV | V |
Lathe | 4 | 1 | 5 | 2 | 5 |
Surface grinder | 3 | 2 | 4 | 3 | 6 |
Solve the following problem :
A foreman wants to process 4 different jobs on three machines: a shaping machine, a drilling machine and a tapping machine, the sequence of operations being shaping-drilling-tapping. Decide the optimal sequence for the four jobs to minimize the total elapsed time. Also find the total elapsed time and the idle time for every machine.
Job | Shaping (Minutes) | Drilling (Minutes) | Trapping (Minutes) |
1 | 13 | 3 | 18 |
2 | 18 | 8 | 4 |
3 | 8 | 6 | 13 |
4 | 23 | 6 | 8 |
If there are n jobs and m machines, then there will be _______ sequence of doing jobs.
______ time is the time when the machine is available but is waiting for a job to be processed
In sequencing problem the time required to transfer a job from one machine to another is ______
State whether the following statement is True or False:
In sequencing problem each job once started on any machine must be processed still its completion
The processing times required for four jobs A, B, C and D on machine M1 are 5, 8, 10 and 7 hours and on machine M2 it requires 7, 4, 3 and 6 hours respectively. The jobs are processed in the order Ml, M2. The sequence that minimises total elapsed time is ______