Advertisements
Advertisements
प्रश्न
Choose the correct alternative:
Assignment Problem is special case of ______
पर्याय
Linear Programming Problem
Unbalanced Problem
Restricted Problem
Sequencing Problem
उत्तर
Linear Programming Problem
APPEARS IN
संबंधित प्रश्न
Suggest optimum solution to the following assignment. Problem, also find the total minimum service time.
Service Time ( in hrs.)
Counters | Salesmen | |||
A | B | C | D | |
W | 41 | 72 | 39 | 52 |
X | 22 | 29 | 49 | 65 |
Y | 27 | 39 | 60 | 51 |
Z | 45 | 50 | 48 | 52 |
Solve the following minimal assignment problem :
Machines | A | B | C | D | E |
M1 | 27 | 18 | ∞ | 20 | 21 |
M2 | 31 | 24 | 21 | 12 | 17 |
M3 | 20 | 17 | 20 | ∞ | 16 |
M4 | 21 | 28 | 20 | 16 | 27 |
Determine `l_92 and l_93, "given that" l_91 = 97, d_91 = 38 and q_92 = 27/59`
A departmental head has three jobs and four subordinates. The subordinates differ in their capabilities and the jobs differ in their work
contents. With the help of the performance matrix given below, find out which of the four subordinates should be assigned which jobs ?
Subordinates | Jobs | ||
I | II | III | |
A | 7 | 3 | 5 |
B | 2 | 7 | 4 |
C | 6 | 5 | 3 |
D | 3 | 4 | 7 |
In a factory there are six jobs to be performed each of which should go through two machines A and B in the order A - B. The processing timing (in hours) for the jobs arc given here. You are required to determine the sequence for performing the jobs that would minimize the total elapsed time T. What is the value of T? Also find the idle time for machines · A and B.
Jobs | J1 | J2 | J3 | J4 | J5 | J6 |
Machine A | 1 | 3 | 8 | 5 | 6 | 3 |
MAchine B | 5 | 6 | 3 | 2 | 2 | 10 |
A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job for each machine is given in the following table:
Jobs | Machines (Processing Cost in ₹) |
|||
P | Q | R | S | |
A | 31 | 25 | 33 | 29 |
B | 25 | 24 | 23 | 21 |
C | 19 | 21 | 23 | 24 |
D | 38 | 36 | 34 | 40 |
Find the optimal assignment to minimize the total processing cost.
Five wagons are available at stations 1, 2, 3, 4, and 5. These are required at 5 stations I, II, III, IV, and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?
I | II | III | IV | V | |
1 | 10 | 5 | 9 | 18 | 11 |
2 | 13 | 9 | 6 | 12 | 14 |
3 | 3 | 2 | 4 | 4 | 5 |
4 | 18 | 9 | 12 | 17 | 15 |
5 | 11 | 6 | 14 | 19 | 10 |
The assignment problem is said to be unbalance if ______
Choose the correct alternative :
In an assignment problem if number of rows is greater than number of columns then
The objective of an assignment problem is to assign ______.
Fill in the blank :
When an assignment problem has more than one solution, then it is _______ optimal solution.
Fill in the blank :
An _______ is a special type of linear programming problem.
In an assignment problem, if number of column is greater than number of rows, then a dummy column is added.
State whether the following is True or False :
It is not necessary to express an assignment problem into n x n matrix.
Solve the following problem :
A plant manager has four subordinates, and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. This estimate of the time each man would take to perform each task is given in the effectiveness matrix below.
I | II | III | IV | |
A | 7 | 25 | 26 | 10 |
B | 12 | 27 | 3 | 25 |
C | 37 | 18 | 17 | 14 |
D | 18 | 25 | 23 | 9 |
How should the tasks be allocated, one to a man, as to minimize the total man hours?
Solve the following problem :
A dairy plant has five milk tankers, I, II, III, IV and V. These milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.
I | II | III | IV | V | |
A | 150 | 120 | 175 | 180 | 200 |
B | 125 | 110 | 120 | 150 | 165 |
C | 130 | 100 | 145 | 160 | 175 |
D | 40 | 40 | 70 | 70 | 100 |
E | 45 | 25 | 60 | 70 | 95 |
How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?
State whether the following statement is True or False:
The objective of an assignment problem is to assign number of jobs to equal number of persons at maximum cost
State whether the following statement is True or False:
In assignment problem, if number of columns is greater than number of rows, then a dummy row is added
State whether the following statement is True or False:
In assignment problem each worker or machine is assigned only one job
What is the Assignment problem?
Three jobs A, B and C one to be assigned to three machines U, V and W. The processing cost for each job machine combination is shown in the matrix given below. Determine the allocation that minimizes the overall processing cost.
Machine | ||||
U | V | W | ||
Jobs | A | 17 | 25 | 31 |
B | 10 | 25 | 16 | |
C | 12 | 14 | 11 |
(cost is in ₹ per unit)
A computer centre has got three expert programmers. The centre needs three application programmes to be developed. The head of the computer centre, after studying carefully the programmes to be developed, estimates the computer time in minitues required by the experts to the application programme as follows.
Programmers | ||||
P | Q | R | ||
Programmers | 1 | 120 | 100 | 80 |
2 | 80 | 90 | 110 | |
3 | 110 | 140 | 120 |
Assign the programmers to the programme in such a way that the total computer time is least.
Find the optimal solution for the assignment problem with the following cost matrix.
Area | |||||
1 | 2 | 3 | 4 | ||
P | 11 | 17 | 8 | 16 | |
Salesman | Q | 9 | 7 | 12 | 6 |
R | 13 | 16 | 15 | 12 | |
S | 14 | 10 | 12 | 11 |
Assign four trucks 1, 2, 3 and 4 to vacant spaces A, B, C, D, E and F so that distance travelled is minimized. The matrix below shows the distance.
1 | 2 | 3 | 4 | |
A | 4 | 7 | 3 | 7 |
B | 8 | 2 | 5 | 5 |
C | 4 | 9 | 6 | 9 |
D | 7 | 5 | 4 | 8 |
E | 6 | 3 | 5 | 4 |
F | 6 | 8 | 7 | 3 |
Choose the correct alternative:
North – West Corner refers to ______
Choose the correct alternative:
The purpose of a dummy row or column in an assignment problem is to
A car hire company has one car at each of five depots a, b, c, d and e. A customer in each of the fine towers A, B, C, D and E requires a car. The distance (in miles) between the depots (origins) and the towers(destinations) where the customers are given in the following distance matrix.
a | b | c | d | e | |
A | 160 | 130 | 175 | 190 | 200 |
B | 135 | 120 | 130 | 160 | 175 |
C | 140 | 110 | 155 | 170 | 185 |
D | 50 | 50 | 80 | 80 | 110 |
E | 55 | 35 | 70 | 80 | 105 |
How should the cars be assigned to the customers so as to minimize the distance travelled?
A dairy plant has five milk tankers, I, II, III, IV and V. Three milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.
I | II | III | IV | V | |
A | 150 | 120 | 175 | 180 | 200 |
B | 125 | 110 | 120 | 150 | 165 |
C | 130 | 100 | 145 | 160 | 170 |
D | 40 | 40 | 70 | 70 | 100 |
E | 45 | 25 | 60 | 70 | 95 |
How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?
A job production unit has four jobs P, Q, R, S which can be manufactured on each of the four machines I, II, III and IV. The processing cost of each job for each machine is given in the following table :
Job | Machines (Processing cost in ₹) |
|||
I | II | III | IV | |
P | 31 | 25 | 33 | 29 |
Q | 25 | 24 | 23 | 21 |
R | 19 | 21 | 23 | 24 |
S | 38 | 36 | 34 | 40 |
Complete the following activity to find the optimal assignment to minimize the total processing cost.
Solution:
Step 1: Subtract the smallest element in each row from every element of it. New assignment matrix is obtained as follows :
Job | Machines (Processing cost in ₹) |
|||
I | II | III | IV | |
P | 6 | 0 | 8 | 4 |
Q | 4 | 3 | 2 | 0 |
R | 0 | 2 | 4 | 5 |
S | 4 | 2 | 0 | 6 |
Step 2: Subtract the smallest element in each column from every element of it. New assignment matrix is obtained as above, because each column in it contains one zero.
Step 3: Draw minimum number of vertical and horizontal lines to cover all zeros:
Job | Machines (Processing cost in ₹) |
|||
I | II | III | IV | |
P | 6 | 0 | 8 | 4 |
Q | 4 | 3 | 2 | 0 |
R | 0 | 2 | 4 | 5 |
S | 4 | 2 | 0 | 6 |
Step 4: From step 3, as the minimum number of straight lines required to cover all zeros in the assignment matrix equals the number of rows/columns. Optimal solution has reached.
Examine the rows one by one starting with the first row with exactly one zero is found. Mark the zero by enclosing it in (`square`), indicating assignment of the job. Cross all the zeros in the same column. This step is shown in the following table :
Job | Machines (Processing cost in ₹) |
|||
I | II | III | IV | |
P | 6 | 0 | 8 | 4 |
Q | 4 | 3 | 2 | 0 |
R | 0 | 2 | 4 | 5 |
S | 4 | 2 | 0 | 6 |
Step 5: It is observed that all the zeros are assigned and each row and each column contains exactly one assignment. Hence, the optimal (minimum) assignment schedule is :
Job | Machine | Min.cost |
P | II | `square` |
Q | `square` | 21 |
R | I | `square` |
S | III | 34 |
Hence, total (minimum) processing cost = 25 + 21 + 19 + 34 = ₹`square`