Advertisements
Advertisements
प्रश्न
State whether the following statement is True or False:
The objective of an assignment problem is to assign number of jobs to equal number of persons at maximum cost
पर्याय
True
False
उत्तर
False
APPEARS IN
संबंधित प्रश्न
A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job is given in the following table:
Jobs
|
Machines |
|||
P |
Q |
R |
S |
|
Processing Cost (Rs.)
|
||||
A |
31 |
25 |
33 |
29 |
B |
25 |
24 |
23 |
21 |
C |
19 |
21 |
23 |
24 |
D |
38 |
36 |
34 |
40 |
How should the jobs be assigned to the four machines so that the total processing cost is minimum?
Suggest optimum solution to the following assignment. Problem, also find the total minimum service time.
Service Time ( in hrs.)
Counters | Salesmen | |||
A | B | C | D | |
W | 41 | 72 | 39 | 52 |
X | 22 | 29 | 49 | 65 |
Y | 27 | 39 | 60 | 51 |
Z | 45 | 50 | 48 | 52 |
Determine `l_92 and l_93, "given that" l_91 = 97, d_91 = 38 and q_92 = 27/59`
Solve the following maximal assignment problem :
Branch Manager | Monthly Business ( Rs. lakh) | |||
A | B | C | D | |
P | 11 | 11 | 9 | 9 |
Q | 13 | 16 | 11 | 10 |
R | 12 | 17 | 13 | 8 |
S | 16 | 14 | 16 | 12 |
Five different machines can do any of the five required jobs, with different profits resulting from each assignment as shown below:
Job | Machines (Profit in ₹) | ||||
A | B | C | D | E | |
1 | 30 | 37 | 40 | 28 | 40 |
2 | 40 | 24 | 27 | 21 | 36 |
3 | 40 | 32 | 33 | 30 | 35 |
4 | 25 | 38 | 40 | 36 | 36 |
5 | 29 | 62 | 41 | 34 | 39 |
Find the optimal assignment schedule.
The assignment problem is said to be balanced if ______.
Choose the correct alternative :
The assignment problem is said to be balanced if it is a ______.
Choose the correct alternative :
In an assignment problem if number of rows is greater than number of columns then
State whether the following is True or False :
In assignment problem, each facility is capable of performing each task.
Solve the following problem :
A plant manager has four subordinates, and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. This estimate of the time each man would take to perform each task is given in the effectiveness matrix below.
I | II | III | IV | |
A | 7 | 25 | 26 | 10 |
B | 12 | 27 | 3 | 25 |
C | 37 | 18 | 17 | 14 |
D | 18 | 25 | 23 | 9 |
How should the tasks be allocated, one to a man, as to minimize the total man hours?
Solve the following problem :
A dairy plant has five milk tankers, I, II, III, IV and V. These milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.
I | II | III | IV | V | |
A | 150 | 120 | 175 | 180 | 200 |
B | 125 | 110 | 120 | 150 | 165 |
C | 130 | 100 | 145 | 160 | 175 |
D | 40 | 40 | 70 | 70 | 100 |
E | 45 | 25 | 60 | 70 | 95 |
How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?
Choose the correct alternative:
The assignment problem is generally defined as a problem of ______
Choose the correct alternative:
Assignment Problem is special case of ______
Choose the correct alternative:
When an assignment problem has more than one solution, then it is ______
If the given matrix is ______ matrix, the assignment problem is called balanced problem
State whether the following statement is True or False:
In assignment problem each worker or machine is assigned only one job
Three jobs A, B and C one to be assigned to three machines U, V and W. The processing cost for each job machine combination is shown in the matrix given below. Determine the allocation that minimizes the overall processing cost.
Machine | ||||
U | V | W | ||
Jobs | A | 17 | 25 | 31 |
B | 10 | 25 | 16 | |
C | 12 | 14 | 11 |
(cost is in ₹ per unit)
Find the optimal solution for the assignment problem with the following cost matrix.
Area | |||||
1 | 2 | 3 | 4 | ||
P | 11 | 17 | 8 | 16 | |
Salesman | Q | 9 | 7 | 12 | 6 |
R | 13 | 16 | 15 | 12 | |
S | 14 | 10 | 12 | 11 |
Assign four trucks 1, 2, 3 and 4 to vacant spaces A, B, C, D, E and F so that distance travelled is minimized. The matrix below shows the distance.
1 | 2 | 3 | 4 | |
A | 4 | 7 | 3 | 7 |
B | 8 | 2 | 5 | 5 |
C | 4 | 9 | 6 | 9 |
D | 7 | 5 | 4 | 8 |
E | 6 | 3 | 5 | 4 |
F | 6 | 8 | 7 | 3 |
Choose the correct alternative:
Number of basic allocation in any row or column in an assignment problem can be
Choose the correct alternative:
If number of sources is not equal to number of destinations, the assignment problem is called ______
Choose the correct alternative:
The purpose of a dummy row or column in an assignment problem is to
Choose the correct alternative:
The solution for an assignment problem is optimal if
Choose the correct alternative:
In an assignment problem involving four workers and three jobs, total number of assignments possible are
A car hire company has one car at each of five depots a, b, c, d and e. A customer in each of the fine towers A, B, C, D and E requires a car. The distance (in miles) between the depots (origins) and the towers(destinations) where the customers are given in the following distance matrix.
a | b | c | d | e | |
A | 160 | 130 | 175 | 190 | 200 |
B | 135 | 120 | 130 | 160 | 175 |
C | 140 | 110 | 155 | 170 | 185 |
D | 50 | 50 | 80 | 80 | 110 |
E | 55 | 35 | 70 | 80 | 105 |
How should the cars be assigned to the customers so as to minimize the distance travelled?
A dairy plant has five milk tankers, I, II, III, IV and V. Three milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.
I | II | III | IV | V | |
A | 150 | 120 | 175 | 180 | 200 |
B | 125 | 110 | 120 | 150 | 165 |
C | 130 | 100 | 145 | 160 | 170 |
D | 40 | 40 | 70 | 70 | 100 |
E | 45 | 25 | 60 | 70 | 95 |
How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?
A job production unit has four jobs P, Q, R, S which can be manufactured on each of the four machines I, II, III and IV. The processing cost of each job for each machine is given in the following table :
Job | Machines (Processing cost in ₹) |
|||
I | II | III | IV | |
P | 31 | 25 | 33 | 29 |
Q | 25 | 24 | 23 | 21 |
R | 19 | 21 | 23 | 24 |
S | 38 | 36 | 34 | 40 |
Complete the following activity to find the optimal assignment to minimize the total processing cost.
Solution:
Step 1: Subtract the smallest element in each row from every element of it. New assignment matrix is obtained as follows :
Job | Machines (Processing cost in ₹) |
|||
I | II | III | IV | |
P | 6 | 0 | 8 | 4 |
Q | 4 | 3 | 2 | 0 |
R | 0 | 2 | 4 | 5 |
S | 4 | 2 | 0 | 6 |
Step 2: Subtract the smallest element in each column from every element of it. New assignment matrix is obtained as above, because each column in it contains one zero.
Step 3: Draw minimum number of vertical and horizontal lines to cover all zeros:
Job | Machines (Processing cost in ₹) |
|||
I | II | III | IV | |
P | 6 | 0 | 8 | 4 |
Q | 4 | 3 | 2 | 0 |
R | 0 | 2 | 4 | 5 |
S | 4 | 2 | 0 | 6 |
Step 4: From step 3, as the minimum number of straight lines required to cover all zeros in the assignment matrix equals the number of rows/columns. Optimal solution has reached.
Examine the rows one by one starting with the first row with exactly one zero is found. Mark the zero by enclosing it in (`square`), indicating assignment of the job. Cross all the zeros in the same column. This step is shown in the following table :
Job | Machines (Processing cost in ₹) |
|||
I | II | III | IV | |
P | 6 | 0 | 8 | 4 |
Q | 4 | 3 | 2 | 0 |
R | 0 | 2 | 4 | 5 |
S | 4 | 2 | 0 | 6 |
Step 5: It is observed that all the zeros are assigned and each row and each column contains exactly one assignment. Hence, the optimal (minimum) assignment schedule is :
Job | Machine | Min.cost |
P | II | `square` |
Q | `square` | 21 |
R | I | `square` |
S | III | 34 |
Hence, total (minimum) processing cost = 25 + 21 + 19 + 34 = ₹`square`
A plant manager has four subordinates and four tasks to perform. The subordinates differ in efficiency and task differ in their intrinsic difficulty. Estimates of the time subordinate would take to perform tasks are given in the following table:
I | II | III | IV | |
A | 3 | 11 | 10 | 8 |
B | 13 | 2 | 12 | 2 |
C | 3 | 4 | 6 | 1 |
D | 4 | 15 | 4 | 9 |
Complete the following activity to allocate tasks to subordinates to minimize total time.
Solution:
Step I: Subtract the smallest element of each row from every element of that row:
I | II | III | IV | |
A | 0 | 8 | 7 | 5 |
B | 11 | 0 | 10 | 0 |
C | 2 | 3 | 5 | 0 |
D | 0 | 11 | 0 | 5 |
Step II: Since all column minimums are zero, no need to subtract anything from columns.
Step III: Draw the minimum number of lines to cover all zeros.
I | II | III | IV | |
A | 0 | 8 | 7 | 5 |
B | 11 | 0 | 10 | 0 |
C | 2 | 3 | 5 | 0 |
D | 0 | 11 | 0 | 5 |
Since minimum number of lines = order of matrix, optimal solution has been reached
Optimal assignment is A →`square` B →`square`
C →IV D →`square`
Total minimum time = `square` hours.