Choose the correct alternative:
The transportation problem is said to be unbalanced if ______
पर्याय
Total supply ≠ Total demand
Total supply = Total demand
m = n
m + n – 1
उत्तर
Total supply ≠ Total demand
APPEARS IN
संबंधित प्रश्न
Write mathematical form of transportation problem
What is feasible solution and non degenerate solution in transportation problem?
What do you mean by balanced transportation problem?
Determine an initial basic feasible solution of the following transportation problem by north west corner method.
Bangalore | Nasik | Bhopal | Delhi | Capacity | |
Chennai | 6 | 8 | 8 | 5 | 30 |
Madurai | 5 | 11 | 9 | 7 | 40 |
Trickly | 8 | 9 | 7 | 13 | 50 |
Demand (Units/day) |
35 | 28 | 32 | 25 |
Find the initial basic feasible solution of the following transportation problem:
I | II | III | Demand | |
A | 1 | 2 | 6 | 7 |
B | 0 | 4 | 2 | 12 |
C | 3 | 1 | 5 | 11 |
Supply | 10 | 10 | 10 |
Using Vogel’s approximation method
Choose the correct alternative:
In a degenerate solution number of allocations is
Choose the correct alternative:
The Penalty in VAM represents difference between the first ______
The following table summarizes the supply, demand and cost information for four factors S1, S2, S3, S4 Shipping goods to three warehouses D1, D2, D3.
D1 | D2 | D3 | Supply | |
S1 | 2 | 7 | 14 | 5 |
S2 | 3 | 3 | 1 | 8 |
S3 | 5 | 4 | 7 | 7 |
S4 | 1 | 6 | 2 | 14 |
Demand | 7 | 9 | 18 |
Find an initial solution by using north west corner rule. What is the total cost for this solution?
Consider the following transportation problem
Destination | Availability | ||||
D1 | D2 | D3 | D4 | ||
O1 | 5 | 8 | 3 | 6 | 30 |
O2 | 4 | 5 | 7 | 4 | 50 |
O3 | 6 | 2 | 4 | 6 | 20 |
Requirement | 30 | 40 | 20 | 10 |
Determine an initial basic feasible solution using Vogel’s approximation method
Determine an initial basic feasible solution to the following transportation problem by using north west corner rule
Destination | Supply | ||||
D1 | D2 | D3 | |||
S1 | 9 | 8 | 5 | 25 | |
Source | S2 | 6 | 8 | 4 | 35 |
S3 | 7 | 6 | 9 | 40 | |
Requirement | 30 | 25 | 45 |