Two Men and Seven Boys Can Do a Work in 14 Days. Three Men and Eight Boys Can Do the Same Work in 11 Days. Further Eight Men and Six Boys Can Do Three Times the Amount of this Work In: - Mathematics

Advertisements
Advertisements

प्रश्न

Choose the most appropriate option.

Two men and seven boys can do work in 14 days. Three men and eight boys can do the same work in 11 days. Further, eight men and six boys can do three times the amount of this work in:

पर्याय

  • 18 days

  • 21 days

  • 30 days

  • 24 days

MCQ

उत्तर

21 days

Explanation:

According to question

(2 × 14) men + (7 × 14) boys = (3 × 11) men + (8 × 11) boys

⇒ 5 men = 10 boys or 1 man = 2 boys

∴ (2 men + 7 boys) = (2 × 2 + 7) boys = 11 boys

(8 men + 6 boys) = (8 × 2 + 6) boys = 22 boys

Let the required number of days be x

According to the ratio proportion,

Boys 22: 11 Work 1: 3] :: 14 : x

∴ (22 × 1 × x) = (11 × 3 × 14)

`∴"x"=462/22=21`

Hence, the required number of days = 21.

shaalaa.com
Time and Work (Entrance Exam)
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
2016-2017 (May) Set 1

संबंधित प्रश्‍न

In a call center, 6 employees working for 10 hours complete a certain task. They started working at 11:00 a.m. This continued till 5.00 pm and after that, for each hour one more employee is added till the work gets completed. At what time will they complete the work?


A, B and C can do a piece of work in 20, 30 and 60 days, respectively. In how many days can A do the work, if he is assisted by B and C on every third day?


A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for ₹ 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?


Pipes P and Q can fill a tank in 5 and 6 h respectively. Pipe R can empty it in 12 h. If all the three pipes are opened together, then the tank will be filled in :


A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:


P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?


Vikas can complete a job in 15 days. Babin can do the same job in 10 days. In how many days can they complete the job if they work together?


Kiran can complete a task in 15 days. He works for 5 days and then leaves. If Venkat completes the remaining task in 30 days, then in how many days can Venkat alone complete the same task?


Two men A and B, each working alone by working 12 hours per day, can complete a work in 20 days. For execution of the work, it was decided that A and B would be working for 8 and 6 hours per day, respectively, on alternate days starting with A. If it takes x days and y hours to complete the work then (x, y) is:


Anil can do a job in 10 days. Sunn is 40% more efficient than Anil. Find the no. of days required by Sunil to do the same job.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×