Question

Choose the most appropriate option.

Two men and seven boys can do work in 14 days. Three men and eight boys can do the same work in 11 days. Further, eight men and six boys can do three times the amount of this work in:

Options

  • 18 days

  • 21 days

  • 30 days

  • 24 days

MCQ

Solution

21 days

Explanation:

According to question

(2 × 14) men + (7 × 14) boys = (3 × 11) men + (8 × 11) boys

⇒ 5 men = 10 boys or 1 man = 2 boys

∴ (2 men + 7 boys) = (2 × 2 + 7) boys = 11 boys

(8 men + 6 boys) = (8 × 2 + 6) boys = 22 boys

Let the required number of days be x

According to the ratio proportion,

Boys 22: 11 Work 1: 3] :: 14 : x

∴ (22 × 1 × x) = (11 × 3 × 14)

`∴"x"=462/22=21`

Hence, the required number of days = 21.

shaalaa.com
Time and Work (Entrance Exam)
  Is there an error in this question or solution?
2016-2017 (May) Set 1

RELATED QUESTIONS

Choose the most appropriate option

‘A’ and ‘B’ complete a work in 12 days, ‘B’ and ‘C’ in 8 days and ‘C’ and ‘A’ in 16 days. ‘A’ left after working for 3 days. In how many days more will ‘B’ and ‘C’ finish the remaining work?


Solve the following question and mark the best possible option.
It takes 8 people working at equal rates to finish work in 96 days. How long will 6 workers take to finish the same work?


A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in


A, B and C can do a piece of work in 20, 30 and 60 days, respectively. In how many days can A do the work, if he is assisted by B and C on every third day?


A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for ₹ 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?


A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:


P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?


Vikas can complete a job in 15 days. Babin can do the same job in 10 days. In how many days can they complete the job if they work together?


8 boys and 12 girls together can finish a project work in 5 days. If it takes 50 days for one boy alone to finish the same project, how many days are required for one girl alone to complete the same project work?


Anil can do a job in 10 days. Sunn is 40% more efficient than Anil. Find the no. of days required by Sunil to do the same job.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×