Advertisements
Advertisements
प्रश्न
Which of the following is not correct?
पर्याय
Objective that we aim to maximize or minimize
Constraints that we need to specify
Decision variables that we need to determine
Decision variables are to be unrestricted.
उत्तर
Decision variables are to be unrestricted.
APPEARS IN
संबंधित प्रश्न
Draw the network for the project whose activities with their relationships are given below:
Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.
Draw the event oriented network for the following data:
Events | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
Immediate Predecessors | - | 1 | 1 | 2, 3 | 3 | 4, 5 | 5, 6 |
Construct the network for the projects consisting of various activities and their precedence relationships are as given below:
A, B, C can start simultaneously A < F, E; B < D, C; E, D < G
A Project has the following time schedule
Activity | 1 - 2 | 1 - 6 | 2 - 3 | 2 - 4 | 3 - 5 | 4 - 5 | 6 - 7 | 5 - 8 | 7 - 8 |
Duration (in days) | 7 | 6 | 14 | 5 | 11 | 7 | 11 | 4 | 18 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
The following table use the activities in a construction projects and relevant information
Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 4 - 5 |
Duration (in days) |
22 | 27 | 12 | 14 | 6 | 12 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
One of the conditions for the activity (i, j) to lie on the critical path is
In constructing the network which one of the following statements is false?
In critical path analysis, the word CPM mean
Draw a network diagram for the following activities.
Activity code | A | B | C | D | E | F | G | H | I | J | K |
Predecessor activity | - | A | A | A | B | C | C | C, D | E, F | G, H | I, J |
Draw the network diagram for the following activities.
Activity code | A | B | C | D | E | F | G |
Predecessor activity | - | - | A | A | B | C | D, E |