मराठी
तामिळनाडू बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य इयत्ता ११

In constructing the network which one of the following statements is false? - Business Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

In constructing the network which one of the following statements is false?

पर्याय

  • Each activity is represented by one and only one arrow. (i.e.) only one activity can connect any two nodes.

  • Two activities can be identified by the same head and tail events.

  • Nodes are numbered to identify an activity uniquely. Tail node (starting point) should be lower than the head node (end point) of an activity.

  • Arrows should not cross each other.

MCQ

उत्तर

Two activities can be identified by the same head and tail events.

shaalaa.com
Network Analysis
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Operations Research - Exercise 10.3 [पृष्ठ २५०]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
पाठ 10 Operations Research
Exercise 10.3 | Q 4 | पृष्ठ २५०

संबंधित प्रश्‍न

A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Jobs 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 5 4 - 6 5 - 6
Duration 6 5 10 3 4 6 2 9

The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


A Project has the following time schedule

Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8
Duration (in days) 7 6 14 5 11 7 11 4 18

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The following table use the activities in a construction projects and relevant information

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5
Duration
(in days)
22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


In a network while numbering the events which one of the following statements is false?


The objective of network analysis is to


Draw a network diagram for the following activities.

Activity code A B C D E F G H I J K
Predecessor activity - A A A B C C C, D E, F G, H I, J

Draw the network diagram for the following activities.

Activity code A B C D E F G
Predecessor activity - - A A B C D, E

The following table gives the characteristics of the project

Activity 1 - 2 1 - 3 2 - 3 3 - 4 3 - 5 4 - 6 5 - 6 6 - 7
Duration
(in days)
5 10 3 4 6 6 5 5

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×