मराठी
तामिळनाडू बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य इयत्ता ११

The following table gives the activities of a project and their duration in days Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5 Duration 5 8 6 7 5 4 8 Construct the network and calculat - Business Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

बेरीज

उत्तर

E1 = 0

E2 = 0 + 5 = 5

E3 = (0 + 8) or (5 + 6)

Whichever is maximum

= 11

E4 = (11 + 5) or (5 + 7)

Whichever is maximum

= 16

E5 = (11 + 4) or (16 + 8)

Whichever is maximum

= 24

L5 = 24

L4 = 24 – 8 = 16

L3 = (24 – 4) or (16 – 5)

whichever is minimum

= 11

L2 = (16 – 6) or (16 – 7)

whichever is minimum

= 5

L1 = (5 – 5) or (11 – 8)

whichever is minimum

L1 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 5 0 5 5 – 5 = 0 5
1 - 3 8 0 8 11 – 8 = 3 11
2 - 3 6 5 11 11 – 6 = 5 11
2 - 4 7 5 12 16 – 7 = 9 16
3 - 4 5 11 16 16 – 5 = 11 16
3 - 5 4 11 15 24 – 4 = 20 24
4 - 5 8 16 24 24 – 8 = 16 24

Since EFT and LFT are same in 1 - 2, 2 - 3, 3 - 4 and 4 - 5.

Hence the critical path is 1 - 2 - 3 - 4 - 5 and the duration time taken is 24 days.

shaalaa.com
Network Analysis
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Operations Research - Exercise 10.2 [पृष्ठ २४९]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
पाठ 10 Operations Research
Exercise 10.2 | Q 8 | पृष्ठ २४९
Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×