हिंदी
तमिलनाडु बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य कक्षा ११

The following table gives the activities of a project and their duration in days Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5 Duration 5 8 6 7 5 4 8 Construct the network and calculat - Business Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

योग

उत्तर

E1 = 0

E2 = 0 + 5 = 5

E3 = (0 + 8) or (5 + 6)

Whichever is maximum

= 11

E4 = (11 + 5) or (5 + 7)

Whichever is maximum

= 16

E5 = (11 + 4) or (16 + 8)

Whichever is maximum

= 24

L5 = 24

L4 = 24 – 8 = 16

L3 = (24 – 4) or (16 – 5)

whichever is minimum

= 11

L2 = (16 – 6) or (16 – 7)

whichever is minimum

= 5

L1 = (5 – 5) or (11 – 8)

whichever is minimum

L1 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 5 0 5 5 – 5 = 0 5
1 - 3 8 0 8 11 – 8 = 3 11
2 - 3 6 5 11 11 – 6 = 5 11
2 - 4 7 5 12 16 – 7 = 9 16
3 - 4 5 11 16 16 – 5 = 11 16
3 - 5 4 11 15 24 – 4 = 20 24
4 - 5 8 16 24 24 – 8 = 16 24

Since EFT and LFT are same in 1 - 2, 2 - 3, 3 - 4 and 4 - 5.

Hence the critical path is 1 - 2 - 3 - 4 - 5 and the duration time taken is 24 days.

shaalaa.com
Network Analysis
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Operations Research - Exercise 10.2 [पृष्ठ २४९]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
अध्याय 10 Operations Research
Exercise 10.2 | Q 8 | पृष्ठ २४९

संबंधित प्रश्न

Draw the network for the project whose activities with their relationships are given below:

Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.


Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:

Activity A B C D E F G H I J K
Immediate Predecessors - - - A B B C D E H, I F, G

A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


A Project has the following time schedule

Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8
Duration (in days) 7 6 14 5 11 7 11 4 18

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The critical path of the following network is


In a network while numbering the events which one of the following statements is false?


The objective of network analysis is to


Network problems have the advantage in terms of project


In critical path analysis, the word CPM mean


A Project has the following time schedule

Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6
Duration
(in days)
6 8 4 9 2 7

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×