हिंदी
तमिलनाडु बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य कक्षा ११

A Project has the following time schedule Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6 Duration(in days) 6 8 4 9 2 7 - Business Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

A Project has the following time schedule

Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6
Duration
(in days)
6 8 4 9 2 7

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.

योग

उत्तर

E1 = 0

E2 = 0 + 6 = 6

E3 = 6 + 8 = 14

E4 = 6 + 4 = 10

E5 = 14 + 9 = 23

E6 = (23 + 7) or (10 + 2)

Whichever is maximum

= 30

L6 = 30

L5 = 30 − 6 = 24

L4 = 30 − 2 = 28

L3 = 23 − 9 = 14

L2 = (14 − 8) or (28 − 4)

Whichever is minimum

= 6

L1 = 6 − 6 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 6 0 6 6 − 6 = 0 6
2 - 3 8 6 14 14 − 8 = 6 14
2 - 4 4 6 10 28 − 4 = 24 28
3 - 5 9 14 23 23 − 9 = 14 23
4 - 6 2 10 22 30 − 28 = 2 4
5 - 6 7 23 30 30 − 7 = 23 30

Since EFT and LFT values are same in 1 - 2, 2 - 3, 3 - 5 and 5 - 6.

Hence the critical path is 1 - 2 - 3 - 5 - 6 and the duration of time taken is 30 days.

shaalaa.com
Network Analysis
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Operations Research - Miscellaneous Problems [पृष्ठ २५२]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
अध्याय 10 Operations Research
Miscellaneous Problems | Q 9 | पृष्ठ २५२

संबंधित प्रश्न

Draw the network for the project whose activities with their relationships are given below:

Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.


Construct the network for the projects consisting of various activities and their precedence relationships are as given below:

A, B, C can start simultaneously A < F, E; B < D, C; E, D < G


Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:

Activity A B C D E F G H I J K
Immediate Predecessors - - - A B B C D E H, I F, G

A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


A Project has the following time schedule

Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8
Duration (in days) 7 6 14 5 11 7 11 4 18

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


In constructing the network which one of the following statements is false?


Which of the following is not correct?


In the context of network, which of the following is not correct


The objective of network analysis is to


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×