हिंदी
तमिलनाडु बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य कक्षा ११

A Project has the following time schedule Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8 Duration (in days) 7 6 14 5 11 7 11 4 18 Construct the network and calculate - Business Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

A Project has the following time schedule

Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8
Duration (in days) 7 6 14 5 11 7 11 4 18

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

योग

उत्तर

E1 = 0

E2 = 0 + 7 = 7

E3 = 7 + 14 = 21

E4 = 7 + 5 = 12

E5 = 21 + 11 or (12 + 7)

Whichever is maximum

= 32

E6 = 0 + 6 = 6

E7 = 6 + 11 = 17

E8 = 17 + 18 = 35

L8 = 35

L7 = 35 – 18 = 17

L6 = 17 – 11 = 6

L5 = 35 – 4 = 31

L4 = 32 – 7 = 25

L3 = 32 – 11 = 21

L2 = (21 – 14) or (25 – 5)

whichever is minimum

= 7

L1 = 7 – 7 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 7 0 7 7 – 7 = 0 7
1 - 6 6 0 6 7 – 6 = 1 7
2 - 3 14 7 21 21 – 14 = 7 21
2 - 4 5 7 12 25 – 5 = 20 25
3 - 5 11 21 32 31 – 11 = 21 32
4 - 5 7 12 19 32 – 25 = 7 14
6 - 7 11 6 17 18 – 11 = 7 18
5 - 8 4 32 36 36 – 4 = 32 36
7 - 8 18 17 36 36 – 18 = 18 36

Since EFT and LFT are same in 1 - 2, 2 - 3, 3 - 5 and 5 - 8.

Hence the critical path is 1 - 2 - 3 - 5 - 8 and the duration of time taken is 36 days.

shaalaa.com
Network Analysis
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Operations Research - Exercise 10.2 [पृष्ठ २४९]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
अध्याय 10 Operations Research
Exercise 10.2 | Q 9 | पृष्ठ २४९

संबंधित प्रश्न

Draw the event oriented network for the following data:

Events 1 2 3 4 5 6 7
Immediate Predecessors - 1 1 2, 3 3 4, 5 5, 6

Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:

Activity A B C D E F G H I J K
Immediate Predecessors - - - A B B C D E H, I F, G

Construct the network for the project whose activities are given below.

Activity 0 - 1 1 - 2 1 - 3 2 - 4 2 - 5 3 - 4 3 - 6 4 - 7 5 - 7 6 - 7
Duration (in week) 3 8 12 6 3 3 8 5 3 8

Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.


A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The critical path of the following network is


Which of the following is not correct?


The objective of network analysis is to


Draw a network diagram for the following activities.

Activity code A B C D E F G H I J K
Predecessor activity - A A A B C C C, D E, F G, H I, J

Draw the network diagram for the following activities.

Activity code A B C D E F G
Predecessor activity - - A A B C D, E

A Project has the following time schedule

Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6
Duration
(in days)
6 8 4 9 2 7

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×