Advertisements
Advertisements
Question
A Project has the following time schedule
Activity | 1 - 2 | 1 - 6 | 2 - 3 | 2 - 4 | 3 - 5 | 4 - 5 | 6 - 7 | 5 - 8 | 7 - 8 |
Duration (in days) | 7 | 6 | 14 | 5 | 11 | 7 | 11 | 4 | 18 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
Solution
E1 = 0
E2 = 0 + 7 = 7
E3 = 7 + 14 = 21
E4 = 7 + 5 = 12
E5 = 21 + 11 or (12 + 7)
Whichever is maximum
= 32
E6 = 0 + 6 = 6
E7 = 6 + 11 = 17
E8 = 17 + 18 = 35
L8 = 35
L7 = 35 – 18 = 17
L6 = 17 – 11 = 6
L5 = 35 – 4 = 31
L4 = 32 – 7 = 25
L3 = 32 – 11 = 21
L2 = (21 – 14) or (25 – 5)
whichever is minimum
= 7
L1 = 7 – 7 = 0
Activity | Duration tij |
EST | EFT = EST + tij | LST = LFT – tij | LFT |
1 - 2 | 7 | 0 | 7 | 7 – 7 = 0 | 7 |
1 - 6 | 6 | 0 | 6 | 7 – 6 = 1 | 7 |
2 - 3 | 14 | 7 | 21 | 21 – 14 = 7 | 21 |
2 - 4 | 5 | 7 | 12 | 25 – 5 = 20 | 25 |
3 - 5 | 11 | 21 | 32 | 31 – 11 = 21 | 32 |
4 - 5 | 7 | 12 | 19 | 32 – 25 = 7 | 14 |
6 - 7 | 11 | 6 | 17 | 18 – 11 = 7 | 18 |
5 - 8 | 4 | 32 | 36 | 36 – 4 = 32 | 36 |
7 - 8 | 18 | 17 | 36 | 36 – 18 = 18 | 36 |
Since EFT and LFT are same in 1 - 2, 2 - 3, 3 - 5 and 5 - 8.
Hence the critical path is 1 - 2 - 3 - 5 - 8 and the duration of time taken is 36 days.
APPEARS IN
RELATED QUESTIONS
Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:
Activity | A | B | C | D | E | F | G | H | I | J | K |
Immediate Predecessors | - | - | - | A | B | B | C | D | E | H, I | F, G |
Construct the network for the project whose activities are given below.
Activity | 0 - 1 | 1 - 2 | 1 - 3 | 2 - 4 | 2 - 5 | 3 - 4 | 3 - 6 | 4 - 7 | 5 - 7 | 6 - 7 |
Duration (in week) | 3 | 8 | 12 | 6 | 3 | 3 | 8 | 5 | 3 | 8 |
Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.
The following table use the activities in a construction projects and relevant information
Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 4 - 5 |
Duration (in days) |
22 | 27 | 12 | 14 | 6 | 12 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
One of the conditions for the activity (i, j) to lie on the critical path is
In constructing the network which one of the following statements is false?
In a network while numbering the events which one of the following statements is false?
In the context of network, which of the following is not correct
The objective of network analysis is to
Draw the network diagram for the following activities.
Activity code | A | B | C | D | E | F | G |
Predecessor activity | - | - | A | A | B | C | D, E |
The following table gives the characteristics of the project
Activity | 1 - 2 | 1 - 3 | 2 - 3 | 3 - 4 | 3 - 5 | 4 - 6 | 5 - 6 | 6 - 7 |
Duration (in days) |
5 | 10 | 3 | 4 | 6 | 6 | 5 | 5 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.