English
Tamil Nadu Board of Secondary EducationHSC Commerce Class 11

A Project has the following time schedule Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8 Duration (in days) 7 6 14 5 11 7 11 4 18 Construct the network and calculate - Business Mathematics and Statistics

Advertisements
Advertisements

Question

A Project has the following time schedule

Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8
Duration (in days) 7 6 14 5 11 7 11 4 18

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Sum

Solution

E1 = 0

E2 = 0 + 7 = 7

E3 = 7 + 14 = 21

E4 = 7 + 5 = 12

E5 = 21 + 11 or (12 + 7)

Whichever is maximum

= 32

E6 = 0 + 6 = 6

E7 = 6 + 11 = 17

E8 = 17 + 18 = 35

L8 = 35

L7 = 35 – 18 = 17

L6 = 17 – 11 = 6

L5 = 35 – 4 = 31

L4 = 32 – 7 = 25

L3 = 32 – 11 = 21

L2 = (21 – 14) or (25 – 5)

whichever is minimum

= 7

L1 = 7 – 7 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 7 0 7 7 – 7 = 0 7
1 - 6 6 0 6 7 – 6 = 1 7
2 - 3 14 7 21 21 – 14 = 7 21
2 - 4 5 7 12 25 – 5 = 20 25
3 - 5 11 21 32 31 – 11 = 21 32
4 - 5 7 12 19 32 – 25 = 7 14
6 - 7 11 6 17 18 – 11 = 7 18
5 - 8 4 32 36 36 – 4 = 32 36
7 - 8 18 17 36 36 – 18 = 18 36

Since EFT and LFT are same in 1 - 2, 2 - 3, 3 - 5 and 5 - 8.

Hence the critical path is 1 - 2 - 3 - 5 - 8 and the duration of time taken is 36 days.

shaalaa.com
Network Analysis
  Is there an error in this question or solution?
Chapter 10: Operations Research - Exercise 10.2 [Page 249]

APPEARS IN

Samacheer Kalvi Business Mathematics and Statistics [English] Class 11 TN Board
Chapter 10 Operations Research
Exercise 10.2 | Q 9 | Page 249

RELATED QUESTIONS

Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:

Activity A B C D E F G H I J K
Immediate Predecessors - - - A B B C D E H, I F, G

Construct the network for the project whose activities are given below.

Activity 0 - 1 1 - 2 1 - 3 2 - 4 2 - 5 3 - 4 3 - 6 4 - 7 5 - 7 6 - 7
Duration (in week) 3 8 12 6 3 3 8 5 3 8

Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.


The following table use the activities in a construction projects and relevant information

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5
Duration
(in days)
22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


One of the conditions for the activity (i, j) to lie on the critical path is


In constructing the network which one of the following statements is false?


In a network while numbering the events which one of the following statements is false?


In the context of network, which of the following is not correct


The objective of network analysis is to


Draw the network diagram for the following activities.

Activity code A B C D E F G
Predecessor activity - - A A B C D, E

The following table gives the characteristics of the project

Activity 1 - 2 1 - 3 2 - 3 3 - 4 3 - 5 4 - 6 5 - 6 6 - 7
Duration
(in days)
5 10 3 4 6 6 5 5

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×