English
Tamil Nadu Board of Secondary EducationHSC Commerce Class 11

The following table use the activities in a construction projects and relevant information Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5 - Business Mathematics and Statistics

Advertisements
Advertisements

Question

The following table use the activities in a construction projects and relevant information

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5
Duration
(in days)
22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.

Sum

Solution

E1 = 0

E2 = 22 + 0 = 22

E3 = (0 + 27) or (22 + 12)

Whichever is maximum

E3 = 34

E4 = (22 + 14) or (34 + 6)

Whichever is maximum

E4 = 40

E5 = 40 + 12 = 52

L5 = 32

L4 = 52 – 12 = 40

L3 = 40 – 6 = 34

L2 = (40 – 14) or (34 – 12)

whichever is minimum

= 22

L1 = 22 – 22 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 22 0 22 22 – 22 = 0 22
1 - 3 27 0 27 34 – 27 = 7 34
2 - 3 12 22 34 34 – 12 = 26 34
2 - 4 14 22 36 40 – 14 = 26 40
3 - 4 6 34 40 40 – 6 = 34 40
4 - 5 12 40 52 52 – 12 = 40 52

Since EFT and LFT are same in 1 - 2, 2 - 3, 3 - 4 and 4 - 5.

Hence the critical path is 1 - 2 - 3 - 4 - 5 and the duration of time taken is 52 days.

shaalaa.com
Network Analysis
  Is there an error in this question or solution?
Chapter 10: Operations Research - Exercise 10.2 [Page 250]

APPEARS IN

Samacheer Kalvi Business Mathematics and Statistics [English] Class 11 TN Board
Chapter 10 Operations Research
Exercise 10.2 | Q 10 | Page 250

RELATED QUESTIONS

Draw the event oriented network for the following data:

Events 1 2 3 4 5 6 7
Immediate Predecessors - 1 1 2, 3 3 4, 5 5, 6

A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Jobs 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 5 4 - 6 5 - 6
Duration 6 5 10 3 4 6 2 9

The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


In constructing the network which one of the following statements is false?


In a network while numbering the events which one of the following statements is false?


Which of the following is not correct?


The objective of network analysis is to


In critical path analysis, the word CPM mean


Draw a network diagram for the following activities.

Activity code A B C D E F G H I J K
Predecessor activity - A A A B C C C, D E, F G, H I, J

Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×