Question
In a network while numbering the events which one of the following statements is false?
Options
Event numbers should be unique.
Event numbering should be carried out on a sequential basis from left to right.
The initial event is numbered 0 or 1.
The head of an arrow should always bear a number lesser than the one assigned at the tail of the arrow.
Solution
The head of an arrow should always bear a number lesser than the one assigned at the tail of the arrow.
APPEARS IN
RELATED QUESTIONS
Draw the network for the project whose activities with their relationships are given below:
Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.
A project schedule has the following characteristics
Activity | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 9 | 5 - 6 | 5 - 7 | 6 - 8 | 7 - 8 | 8 - 10 | 9 - 10 |
Time | 4 | 1 | 1 | 1 | 6 | 5 | 4 | 8 | 1 | 2 | 5 | 7 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
The following table gives the activities of a project and their duration in days
Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 5 |
Duration | 5 | 8 | 6 | 7 | 5 | 4 | 8 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
One of the conditions for the activity (i, j) to lie on the critical path is
In constructing the network which one of the following statements is false?
Which of the following is not correct?
The objective of network analysis is to
In critical path analysis, the word CPM mean
Draw a network diagram for the following activities.
Activity code | A | B | C | D | E | F | G | H | I | J | K |
Predecessor activity | - | A | A | A | B | C | C | C, D | E, F | G, H | I, J |
The following table gives the characteristics of the project
Activity | 1 - 2 | 1 - 3 | 2 - 3 | 3 - 4 | 3 - 5 | 4 - 6 | 5 - 6 | 6 - 7 |
Duration (in days) |
5 | 10 | 3 | 4 | 6 | 6 | 5 | 5 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.