Advertisements
Advertisements
Question
The following table gives the characteristics of the project
Activity | 1 - 2 | 1 - 3 | 2 - 3 | 3 - 4 | 3 - 5 | 4 - 6 | 5 - 6 | 6 - 7 |
Duration (in days) |
5 | 10 | 3 | 4 | 6 | 6 | 5 | 5 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
Solution
E1 = 0
E2 = 0 + 5 = 5
E3 = (5 + 3) or (0 + 10)
Whichever is maximum
= 10
E4 = 10 + 4 = 14
E5 = 10 + 6 = 16
E6 = (14 + 6) or (16 + 5)
Whichever is maximum
= 21
E7 = 21 + 5 = 26
L7 = 26
L6 = 26 − 5 = 21
L5 = 21 − 5 = 16
L4 = 21 − 6 = 15
L3 = (15 − 4) or (16 − 6)
Whichever is minimum
= 10
L2 = 10 − 3 = 7
L1 = (7 − 5) or (10 − 10)
Whichever is minimum
L1 = 0
Activity | Duration tij |
EST | EFT = EST + tij | LST = LFT – tij | LFT |
1 - 2 | 5 | 0 | 5 | 7 − 5 = 2 | 7 |
1 - 3 | 10 | 0 | 10 | 10 − 10 = 0 | 10 |
2 - 3 | 3 | 5 | 8 | 10 − 3 = 7 | 10 |
3 - 4 | 4 | 10 | 14 | 15 − 4 = 11 | 15 |
3 - 5 | 6 | 10 | 16 | 16 − 6 = 10 | 16 |
4 - 6 | 6 | 14 | 20 | 21 − 6 = 15 | 21 |
5 - 6 | 5 | 16 | 21 | 21 − 5 = 16 | 21 |
6 - 7 | 5 | 21 | 26 | 26 − 5 = 21 | 26 |
Since EFT and LFT values are same in 1 - 3, 3 - 5, 5 - 6 and 6 - 7.
Hence the critical path is 1 - 3 - 5 - 6 - 7 and the duration of time taken is 26 days.
APPEARS IN
RELATED QUESTIONS
Draw the event oriented network for the following data:
Events | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
Immediate Predecessors | - | 1 | 1 | 2, 3 | 3 | 4, 5 | 5, 6 |
Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:
Activity | A | B | C | D | E | F | G | H | I | J | K |
Immediate Predecessors | - | - | - | A | B | B | C | D | E | H, I | F, G |
A project schedule has the following characteristics
Activity | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 9 | 5 - 6 | 5 - 7 | 6 - 8 | 7 - 8 | 8 - 10 | 9 - 10 |
Time | 4 | 1 | 1 | 1 | 6 | 5 | 4 | 8 | 1 | 2 | 5 | 7 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
Jobs | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 5 | 4 - 6 | 5 - 6 |
Duration | 6 | 5 | 10 | 3 | 4 | 6 | 2 | 9 |
The following table gives the activities of a project and their duration in days
Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 5 |
Duration | 5 | 8 | 6 | 7 | 5 | 4 | 8 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
In constructing the network which one of the following statements is false?
Network problems have the advantage in terms of project
In critical path analysis, the word CPM mean
Draw a network diagram for the following activities.
Activity code | A | B | C | D | E | F | G | H | I | J | K |
Predecessor activity | - | A | A | A | B | C | C | C, D | E, F | G, H | I, J |
A Project has the following time schedule
Activity | 1 - 2 | 2 - 3 | 2 - 4 | 3 - 5 | 4 - 6 | 5 - 6 |
Duration (in days) |
6 | 8 | 4 | 9 | 2 | 7 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.