English
Tamil Nadu Board of Secondary EducationHSC Commerce Class 11

One of the conditions for the activity (i, j) to lie on the critical path is - Business Mathematics and Statistics

Advertisements
Advertisements

Question

One of the conditions for the activity (i, j) to lie on the critical path is

Options

  • Ej – Ei = Lj – Li = tij

  • Ei – Ej = Lj – Li = tij

  • Ej – Ei = Li – Lj = tij

  • Ej – Ei = Lj – Li ≠ tij

MCQ

Solution

Ej – Ei = Lj – Li = tij

shaalaa.com
Network Analysis
  Is there an error in this question or solution?
Chapter 10: Operations Research - Exercise 10.3 [Page 250]

APPEARS IN

Samacheer Kalvi Business Mathematics and Statistics [English] Class 11 TN Board
Chapter 10 Operations Research
Exercise 10.3 | Q 3 | Page 250

RELATED QUESTIONS

Draw the event oriented network for the following data:

Events 1 2 3 4 5 6 7
Immediate Predecessors - 1 1 2, 3 3 4, 5 5, 6

A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Jobs 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 5 4 - 6 5 - 6
Duration 6 5 10 3 4 6 2 9

The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


A Project has the following time schedule

Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8
Duration (in days) 7 6 14 5 11 7 11 4 18

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


In the context of network, which of the following is not correct


In critical path analysis, the word CPM mean


Draw a network diagram for the following activities.

Activity code A B C D E F G H I J K
Predecessor activity - A A A B C C C, D E, F G, H I, J

A Project has the following time schedule

Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6
Duration
(in days)
6 8 4 9 2 7

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


The following table gives the characteristics of the project

Activity 1 - 2 1 - 3 2 - 3 3 - 4 3 - 5 4 - 6 5 - 6 6 - 7
Duration
(in days)
5 10 3 4 6 6 5 5

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×