English
Tamil Nadu Board of Secondary EducationHSC Commerce Class 11

The objective of network analysis is to - Business Mathematics and Statistics

Advertisements
Advertisements

Question

The objective of network analysis is to

Options

  • Minimize total project cost

  • Minimize total project duration

  • Minimize production delays, interruption and conflicts

  • All the above

MCQ

Solution

Minimize total project duration

shaalaa.com
Network Analysis
  Is there an error in this question or solution?
Chapter 10: Operations Research - Exercise 10.3 [Page 251]

APPEARS IN

Samacheer Kalvi Business Mathematics and Statistics [English] Class 11 TN Board
Chapter 10 Operations Research
Exercise 10.3 | Q 12 | Page 251

RELATED QUESTIONS

Draw the network for the project whose activities with their relationships are given below:

Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.


Draw the event oriented network for the following data:

Events 1 2 3 4 5 6 7
Immediate Predecessors - 1 1 2, 3 3 4, 5 5, 6

Construct the network for the projects consisting of various activities and their precedence relationships are as given below:

A, B, C can start simultaneously A < F, E; B < D, C; E, D < G


A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


One of the conditions for the activity (i, j) to lie on the critical path is


In a network while numbering the events which one of the following statements is false?


Which of the following is not correct?


In the context of network, which of the following is not correct


Draw the network diagram for the following activities.

Activity code A B C D E F G
Predecessor activity - - A A B C D, E

The following table gives the characteristics of the project

Activity 1 - 2 1 - 3 2 - 3 3 - 4 3 - 5 4 - 6 5 - 6 6 - 7
Duration
(in days)
5 10 3 4 6 6 5 5

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×