English
Tamil Nadu Board of Secondary EducationHSC Commerce Class 11

Construct the network for the project whose activities are given below. Activity 0 - 1 1 - 2 1 - 3 2 - 4 2 - 5 3 - 4 3 - 6 4 - 7 5 - 7 6 - 7 Duration (in week) 3 8 12 6 3 3 8 5 3 8 - Business Mathematics and Statistics

Advertisements
Advertisements

Question

Construct the network for the project whose activities are given below.

Activity 0 - 1 1 - 2 1 - 3 2 - 4 2 - 5 3 - 4 3 - 6 4 - 7 5 - 7 6 - 7
Duration (in week) 3 8 12 6 3 3 8 5 3 8

Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.

Sum

Solution

E1 = 0 + 3 = 3

E2 = E1 + t12 = 8 + 3 = 11

E3 = 3 + 12 = 15

E4 = 15 + 3 = 18

E5 = E2 + 3 = 11 + 3 = 14

E6 = E3 + 8 = 15 + 8 = 23

E7 = E6 + 8 = 23 + 8 = 31

L7 = 31

L6 = L7 – 8 = 31 – 8 = 23

L5 = L7 – 3 = 31 – 3 = 28

L4 = L7 – 5 = 31 – 5 = 26

L3 = L6 – 8 = 23 – 8 = 15

L2 = L5 – 3 or L4 which is minimum

= (28 – 3) or (26 – 6)

= 25 or 20

= 20 (which is minimum)

L1 = L2 – 8 or L3 – 12

whichever is minimum

= (20 – 8) or (15 – 12)

= 12 or 3

= 3

L0 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
0 - 1 3 0 3 3 3
1 - 2 8 3 11 20 – 8 = 12 20
1 - 3 12 3 15 15 – 12 = 3 15
2 - 4 6 11 17 26 – 6= 20 26
2 - 5 3 11 14 28 – 3 = 25 28
3 - 4 3 15 18 26 – 3 = 23 26
3 - 6 8 15 23 23 – 8 = 15 23
4 - 7 5 18 23 31 – 5 = 26 31
5 - 7 3 14 14 31 – 3 = 28 31
6 - 7 8 23 31 31 – 8 = 23 31

The critical path is 0 - 1 - 3 - 6 - 7 and the project completion time is 31 weeks.

shaalaa.com
Network Analysis
  Is there an error in this question or solution?
Chapter 10: Operations Research - Exercise 10.2 [Page 249]

APPEARS IN

Samacheer Kalvi Business Mathematics and Statistics [English] Class 11 TN Board
Chapter 10 Operations Research
Exercise 10.2 | Q 5 | Page 249

RELATED QUESTIONS

Construct the network for the projects consisting of various activities and their precedence relationships are as given below:

A, B, C can start simultaneously A < F, E; B < D, C; E, D < G


Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:

Activity A B C D E F G H I J K
Immediate Predecessors - - - A B B C D E H, I F, G

A Project has the following time schedule

Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8
Duration (in days) 7 6 14 5 11 7 11 4 18

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


One of the conditions for the activity (i, j) to lie on the critical path is


Which of the following is not correct?


In the context of network, which of the following is not correct


Draw a network diagram for the following activities.

Activity code A B C D E F G H I J K
Predecessor activity - A A A B C C C, D E, F G, H I, J

Draw the network diagram for the following activities.

Activity code A B C D E F G
Predecessor activity - - A A B C D, E

A Project has the following time schedule

Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6
Duration
(in days)
6 8 4 9 2 7

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


The following table gives the characteristics of the project

Activity 1 - 2 1 - 3 2 - 3 3 - 4 3 - 5 4 - 6 5 - 6 6 - 7
Duration
(in days)
5 10 3 4 6 6 5 5

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×