हिंदी
तमिलनाडु बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य कक्षा ११

The critical path of the following network is - Business Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

The critical path of the following network is

विकल्प

  • 1 - 2 - 4 - 5

  • 1 - 3 - 5

  • 1 - 2 - 3 - 5

  • 1 - 2 - 3 - 4 - 5

MCQ

उत्तर

1 - 2 - 3 - 4 - 5

Explanation:

1 - 2 - 4 - 5 ⇒ EFT = 20 + 12 + 10 = 42

1 - 3 - 5 ⇒ EFT = 25 + 8 = 33

1 - 2 - 3 - 5 ⇒ EFT = 20 + 10 + 8 = 38

1 - 2 - 3 - 4 - 5 ⇒ EFT = 20 + 10 + 5 + 10 = 45

shaalaa.com
Network Analysis
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Operations Research - Exercise 10.3 [पृष्ठ २५०]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
अध्याय 10 Operations Research
Exercise 10.3 | Q 1 | पृष्ठ २५०

संबंधित प्रश्न

Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Jobs 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 5 4 - 6 5 - 6
Duration 6 5 10 3 4 6 2 9

A Project has the following time schedule

Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8
Duration (in days) 7 6 14 5 11 7 11 4 18

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The following table use the activities in a construction projects and relevant information

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5
Duration
(in days)
22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


One of the conditions for the activity (i, j) to lie on the critical path is


In a network while numbering the events which one of the following statements is false?


Which of the following is not correct?


The objective of network analysis is to


Network problems have the advantage in terms of project


In critical path analysis, the word CPM mean


Draw the network diagram for the following activities.

Activity code A B C D E F G
Predecessor activity - - A A B C D, E

Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×