हिंदी
तमिलनाडु बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य कक्षा ११

Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path - Business Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Jobs 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 5 4 - 6 5 - 6
Duration 6 5 10 3 4 6 2 9
योग

उत्तर

E1 = 0

E2 = 0 + 6 = 6

E3 = 0 + 5 = 5

E4 = 6 + 10 = 16

E5 = (5 + 4) or (16 + 6)

Whichever is maximum

= 22

E6 = (16 + 2) or (22 + 9)

Whichever is maximum

 = 31

L= 31

L5 = 31 – 8 = 22

L4 = 22 – 6 = 16 or (31 – 2)

whichever is minimum

L3 = 22 – 4 = 18

L2 = 16 – 10 = 6

L1 = 6 – 6 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 6 0 6 6 – 6 = 0 6
1 - 3 5 0 5 18 – 5 = 13 18
2 - 4 10 6 16 16 – 10 = 6 16
3 - 4 3 5 8 16 – 3 = 13 16
3 - 5 4 5 9 22 – 4 = 18 22
4 - 5 6 16 22 22 – 6 = 16 22
4 - 6 2 16 18 31 – 2 = 29 31
5 - 6 9 22 31 31 – 9 = 22 31

Since EFT and LFT is same on 1 - 2, 2 - 4, 4 - 5 and 5 - 6, the critical path is 1 - 2 - 4 - 5 - 6 and duration time taken is 31 days.

shaalaa.com
Network Analysis
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Operations Research - Exercise 10.2 [पृष्ठ २४९]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
अध्याय 10 Operations Research
Exercise 10.2 | Q 7 | पृष्ठ २४९
Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×