Advertisements
Advertisements
प्रश्न
Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:
Activity | A | B | C | D | E | F | G | H | I | J | K |
Immediate Predecessors | - | - | - | A | B | B | C | D | E | H, I | F, G |
उत्तर
APPEARS IN
संबंधित प्रश्न
Draw the event oriented network for the following data:
Events | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
Immediate Predecessors | - | 1 | 1 | 2, 3 | 3 | 4, 5 | 5, 6 |
A project schedule has the following characteristics
Activity | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 9 | 5 - 6 | 5 - 7 | 6 - 8 | 7 - 8 | 8 - 10 | 9 - 10 |
Time | 4 | 1 | 1 | 1 | 6 | 5 | 4 | 8 | 1 | 2 | 5 | 7 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
The following table gives the activities of a project and their duration in days
Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 5 |
Duration | 5 | 8 | 6 | 7 | 5 | 4 | 8 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
A Project has the following time schedule
Activity | 1 - 2 | 1 - 6 | 2 - 3 | 2 - 4 | 3 - 5 | 4 - 5 | 6 - 7 | 5 - 8 | 7 - 8 |
Duration (in days) | 7 | 6 | 14 | 5 | 11 | 7 | 11 | 4 | 18 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
The following table use the activities in a construction projects and relevant information
Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 4 - 5 |
Duration (in days) |
22 | 27 | 12 | 14 | 6 | 12 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
One of the conditions for the activity (i, j) to lie on the critical path is
In constructing the network which one of the following statements is false?
In a network while numbering the events which one of the following statements is false?
Which of the following is not correct?
Draw the network diagram for the following activities.
Activity code | A | B | C | D | E | F | G |
Predecessor activity | - | - | A | A | B | C | D, E |