A Project has the following time schedule Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6 Duration(in days) 6 8 4 9 2 7 - Business Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

A Project has the following time schedule

Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6
Duration
(in days)
6 8 4 9 2 7

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.

बेरीज

उत्तर

E1 = 0

E2 = 0 + 6 = 6

E3 = 6 + 8 = 14

E4 = 6 + 4 = 10

E5 = 14 + 9 = 23

E6 = (23 + 7) or (10 + 2)

Whichever is maximum

= 30

L6 = 30

L5 = 30 − 6 = 24

L4 = 30 − 2 = 28

L3 = 23 − 9 = 14

L2 = (14 − 8) or (28 − 4)

Whichever is minimum

= 6

L1 = 6 − 6 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 6 0 6 6 − 6 = 0 6
2 - 3 8 6 14 14 − 8 = 6 14
2 - 4 4 6 10 28 − 4 = 24 28
3 - 5 9 14 23 23 − 9 = 14 23
4 - 6 2 10 22 30 − 28 = 2 4
5 - 6 7 23 30 30 − 7 = 23 30

Since EFT and LFT values are same in 1 - 2, 2 - 3, 3 - 5 and 5 - 6.

Hence the critical path is 1 - 2 - 3 - 5 - 6 and the duration of time taken is 30 days.

shaalaa.com
Network Analysis
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Operations Research - Miscellaneous Problems [पृष्ठ २५२]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
पाठ 10 Operations Research
Miscellaneous Problems | Q 9 | पृष्ठ २५२