Advertisements
Advertisements
प्रश्न
A Project has the following time schedule
Activity | 1 - 2 | 2 - 3 | 2 - 4 | 3 - 5 | 4 - 6 | 5 - 6 |
Duration (in days) |
6 | 8 | 4 | 9 | 2 | 7 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
उत्तर
E1 = 0
E2 = 0 + 6 = 6
E3 = 6 + 8 = 14
E4 = 6 + 4 = 10
E5 = 14 + 9 = 23
E6 = (23 + 7) or (10 + 2)
Whichever is maximum
= 30
L6 = 30
L5 = 30 − 6 = 24
L4 = 30 − 2 = 28
L3 = 23 − 9 = 14
L2 = (14 − 8) or (28 − 4)
Whichever is minimum
= 6
L1 = 6 − 6 = 0
Activity | Duration tij |
EST | EFT = EST + tij | LST = LFT – tij | LFT |
1 - 2 | 6 | 0 | 6 | 6 − 6 = 0 | 6 |
2 - 3 | 8 | 6 | 14 | 14 − 8 = 6 | 14 |
2 - 4 | 4 | 6 | 10 | 28 − 4 = 24 | 28 |
3 - 5 | 9 | 14 | 23 | 23 − 9 = 14 | 23 |
4 - 6 | 2 | 10 | 22 | 30 − 28 = 2 | 4 |
5 - 6 | 7 | 23 | 30 | 30 − 7 = 23 | 30 |
Since EFT and LFT values are same in 1 - 2, 2 - 3, 3 - 5 and 5 - 6.
Hence the critical path is 1 - 2 - 3 - 5 - 6 and the duration of time taken is 30 days.
APPEARS IN
संबंधित प्रश्न
Draw the network for the project whose activities with their relationships are given below:
Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.
Construct the network for the projects consisting of various activities and their precedence relationships are as given below:
A, B, C can start simultaneously A < F, E; B < D, C; E, D < G
Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:
Activity | A | B | C | D | E | F | G | H | I | J | K |
Immediate Predecessors | - | - | - | A | B | B | C | D | E | H, I | F, G |
The following table use the activities in a construction projects and relevant information
Activity | 1 - 2 | 1 - 3 | 2 - 3 | 2 - 4 | 3 - 4 | 4 - 5 |
Duration (in days) |
22 | 27 | 12 | 14 | 6 | 12 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
In constructing the network which one of the following statements is false?
Which of the following is not correct?
Network problems have the advantage in terms of project
In critical path analysis, the word CPM mean
Draw a network diagram for the following activities.
Activity code | A | B | C | D | E | F | G | H | I | J | K |
Predecessor activity | - | A | A | A | B | C | C | C, D | E, F | G, H | I, J |
Draw the network diagram for the following activities.
Activity code | A | B | C | D | E | F | G |
Predecessor activity | - | - | A | A | B | C | D, E |