मराठी
तामिळनाडू बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य इयत्ता ११

A project schedule has the following characteristics Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10 Time 4 1 1 1 6 5 4 8 1 2 5 7 - Business Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

बेरीज

उत्तर

E1 = 0

E2 = 0 + 4 = 4

E3 = 0 + 1 = 1

E4 = 4 + 1 = 5

E5 = 1 + 6 = 7

E6 = 7 + 4 = 11

E7 = 8 + 7 = 15

E8 = 15 + 2 = 7

E9 = 5 + 5 = 10

E10 = 17 + 5 = 22

L7 = 31

L10 = 22

L9 = 22 – 7 = 15

L8 = 22 – 5 = 17

L7 = 17 – 2 = 15

L= 17 – 1 = 16

L5 = (16 – 4) or (15 – 8)

whichever is minimum = 7

L4 = 15 – 5 = 10

L3 = (10 – 1) or (7 – 6)

whichever is minimum = 1

L2 = 10 – 1 = 9

L1 = 0

Activity Duration
tij
EST EFT = EST + tij LST = LFT – tij LFT
1 - 2 4 0 4 9 – 4 = 5 9
1 - 3 1 0 1 1 – 1 = 0 1
2 - 4 1 4 5 10 – 1 = 9 10
3 - 4 1 1 2 10 – 1 = 9 10
3 - 5 6 1 7 7 – 6 =1 7
4 - 9 5 5 10 15 – 5 =10 15
5 - 6 4 7 11 16  4 = 12 16
5 - 7 8 7 15 15 – 8 = 7 15
6 - 8 1 11 12 17 – 1 = 16 17
7 - 8 2 15 17 17 – 2 = 15 17
8 - 10 5 17 22 22 – 5 = 17 22
9 - 10 7 10 17 22 – 7 = 15 22

Since EFT and LFT is same on 1 - 3, 3 - 5, 5 - 7 and 7 - 8 and 8 - 10 the critical path is 1 - 3 - 5 - 7 - 8 - 10 and the duration is 22 time units.

shaalaa.com
Network Analysis
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 10: Operations Research - Exercise 10.2 [पृष्ठ २४९]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
पाठ 10 Operations Research
Exercise 10.2 | Q 6 | पृष्ठ २४९

संबंधित प्रश्‍न

Draw the network for the project whose activities with their relationships are given below:

Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.


Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:

Activity A B C D E F G H I J K
Immediate Predecessors - - - A B B C D E H, I F, G

Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Jobs 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 5 4 - 6 5 - 6
Duration 6 5 10 3 4 6 2 9

The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The following table use the activities in a construction projects and relevant information

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5
Duration
(in days)
22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


In constructing the network which one of the following statements is false?


In the context of network, which of the following is not correct


Network problems have the advantage in terms of project


In critical path analysis, the word CPM mean


A Project has the following time schedule

Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6
Duration
(in days)
6 8 4 9 2 7

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×