10 boys can dig a pitch in 12 hours. How long will 8 boys take to do it?
Options
9 h 36 min
15 h
6 h 40 min
13 h 20 min
Solution
15 h
Time is taken by 10 boys to dig a pitch = 12 hours
Time is taken by 1 boy to dig a pitch = 12 × 10 = 120 hours (less boys means more time)
Time is taken by 8 boys to dig a pitch = `120/8` = 15 hours
APPEARS IN
RELATED QUESTIONS
If (p – x) : (q – x) be the duplicate ratio of p : q then show that : `1/p + 1/q = 1/x`.
Convert the following percentage to fractions and ratio:
2.5%
What quantity must be added to each term of the ratio 19 : 51 to make it equal to 3 : 7 ?
If a,b,c are in continued proportion,
show that: `("a"^2 + "b"^2)/("b"("a" + "c")` = `("b"("a" + "c"))/("b"^2 + "c"^2)`
Express the given ratio in its simplest form: `6 1/4 : 12 1/2`
If a : b = 1.5 : 3.5 and b : c = 5 : 6, find a : c.
In a class, one out of every 5 students pass. If there are 225 students in all the sections of a class, find how many pass?
If x : y = 2 : 3, and y : z = 4 : 7, find x : y : z
Divide Rs 3450 among A, B, and C in the ratio 3 : 5 : 7.
An alloy contains only zinc and copper and they are in the ratio of 7:9. If the weight of the alloy is 8 kg, then find the weight of copper in the alloy.