Question

40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?

Sum

Solution

Number of men required to complete the work in 26 days = 40

Number of men required to complete the work in 1 day = 40 × 26 = 1040 men (less men more days)

Number of men required to complete the work in 16 days = `1040/16` = 65