Question
A can do a piece of work in 12 hours, B and C can do it 3 hours whereas A and C can do it in 6 hours. How long will B alone take to do the same work?
Solution
Time taken by A to complete the work = 12 hours.
∴ A’s 1 hour work = `1/12` ...(1)
(B + C) complete the work in 3 hours.
∴ (B + C)’s 1 hour work = `1/3` ...(2)
Add (1) and (2)
∴ (A + B + C)’s 1 hour work = `1/12 + 1/3`
= `(1 + 4)/12`
= `5/12`
Now (A + C) complete the work in 6 hours.
∴(A + C)’s 1 hour work = `1/6`
∴ B’s 1 hour work = (A + B + C)’s 1 hour work – (A + C)’s 1 hour work
= `5/12 - 1/6`
= `(5 - 2)/12`
= `3/12`
= `1/4`
∴ B alone take 4 days to complete the work.
APPEARS IN
RELATED QUESTIONS
A can finish a job in 3 days whereas B finishes it in 6 days. The time taken to complete the job working together is __________ days
A can do a work in 24 days. If A and B together can finish the work in 6 days, then B alone can finish the work in ________ days
A alone can do a piece of work in 35 days. If B is 40% more efficient than A, then B will finish the work in ___________ days
210 men working 12 hours a day can finish a job in 18 days. How many men are required to finish the job in 20 days working 14 hours a day?
If 6 container lorries can transport 135 tonnes of goods in 5 days, how many more lorries are required to transport 180 tonnes of goods in 4 days?
Carpenter A takes 15 minutes to fit the parts of a chair while Carpenter B takes 3 minutes more than A to do the same work. Working together, how long will it take for them to fit the parts for 22 chairs?
A can do a work In 45 days. He works at it for 15 days and then, B alone finishes the remaining work in 24 days. Find the time taken to complete 80% of the work, if they work together
A is thrice as fast as B. If B can do a piece of work in 24 days then, find the number of days they will take to complete the work together
If 32 men working 12 hours a day can do a work in 15 days, then how many men working 10 hours a day can do double that work in 24 days?
A small-scale company undertakes an agreement to make 540 motor pumps in 150 days and employs 40 men for the work. After 75 days, the company could make only 180 motor pumps. How many more men should the company employees so that the work is completed on time as per the agreement?