प्रश्न

If 36 men can do a piece of work in 25 days, in how many days will 15 men do it?

 
टिप्पणी लिखिए

उत्तर

Let x be the number of days in which 15 men can do a piece of work.

Number of men 36 15
Number of days 25 x

 Since the number of men hired and the number of days taken to do a piece of work are in inverse variation, we have :
36×25=x×15
x=36×2515
=90015
=60
 Thus, the required number of days is 60 .

shaalaa.com
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Direct and Inverse Variations - Exercise 10.2 [पृष्ठ १३]

APPEARS IN

आरडी शर्मा Mathematics [English] Class 8
अध्याय 10 Direct and Inverse Variations
Exercise 10.2 | Q 5 | पृष्ठ १३

वीडियो ट्यूटोरियलVIEW ALL [1]

Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×
Our website is made possible by ad-free subscriptions or displaying online advertisements to our visitors.
If you don't like ads you can support us by buying an ad-free subscription or please consider supporting us by disabling your ad blocker. Thank you.