प्रश्न
Which of the following quantities vary inversely as other?
The number of x men hired to construct a wall and the time y taken to finish the job.
उत्तर
If the number of men is more, the time taken to construct a wall will be less. Therefore, it is in inverse variation.
Thus, only is in inverse variation.
APPEARS IN
संबंधित प्रश्न
A farmer has enough food to feed 20 animals in his cattle for 6 days. How long would the food last if there were 10 more animals in his cattle?
In which of the following table x and y vary inversely:
x | 5 | 20 | 10 | 4 |
y | 20 | 5 | 10 | 25 |
It x and y vary inversely, fill in the following blank:
x | 9 | ... | 81 | 243 |
y | 27 | 9 | ... | 1 |
Which of the following quantities vary inversely as other?
The length x of a journey by bus and price y of the ticket.
A work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men?
1200 men can finish a stock of food in 35 days. How many more men should join them so that the same stock may last for 25 days?
A farmer has enough food for 144 ducks for 28 days. If he sells 32 ducks how long will the food last?
Meena had enough money to send 8 parcels each weighing 500 grams through a courier service. What would be the weight of each parcel, if she has to send 40 parcels for the same money?
If two quantities p and q vary inversely with each other then ______ of their corresponding values remains constant.
Sobi types 108 words in 6 minutes. How many words would she type in half an hour?