A work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men? - Mathematics

Advertisements
Advertisements

Question

A work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men? 

Short Note

Solution

Let x be the number days required to complete a piece of work by 125 men.
 

Number of men 50 125
Months 5 x

 Since the number of men engaged and the number of days taken to do a piece of work are in inverse variation, we have: 
50×5=125x
x=50×5125
=2
 Thus, the required number of months is 2 .

shaalaa.com
  Is there an error in this question or solution?
Chapter 10: Direct and Inverse Variations - Exercise 10.2 [Page 13]

APPEARS IN

RD Sharma Mathematics [English] Class 8
Chapter 10 Direct and Inverse Variations
Exercise 10.2 | Q 6 | Page 13

Video TutorialsVIEW ALL [1]

Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×
Our website is made possible by ad-free subscriptions or displaying online advertisements to our visitors.
If you don't like ads you can support us by buying an ad-free subscription or please consider supporting us by disabling your ad blocker. Thank you.