Advertisements
Advertisements
Question
A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?
Solution
Let x be the extra number of men employed to complete the job in 7 months.
Number of men | 420 | x |
Months | 9 | 7 |
\[\text{ Since the number of men hired and the time required to finish the piece of work are in inverse variation, we have } : \]
\[420 \times 9 = 7x\]
\[ \Rightarrow x = \frac{420 \times 9}{7}\]
\[ = 540\]
\[\text{ Thus, the number of extra men required to complete the job in 7 months } = 540 - 420 = 120\]
APPEARS IN
RELATED QUESTIONS
Which of the following are in inverse proportion?
The time taken for a fixed journey and the speed of the vehicle.
In which of the following table x and y vary inversely:
x | 9 | 24 | 15 | 3 |
y | 8 | 3 | 4 | 25 |
If x and y vary inversely as other and y = 35, find x when constant of variation = 7.
Six men can complete a work in 12 days. Two days later, 6 more men joined them. How many days will they take to complete the remaining work?
If p and q are in inverse variation then (p + 2) and (q – 2) are also in inverse proportion.
Write whether the following statement vary directly, vary inversely with each other, or neither of the two.
Compound interest on a given sum and the sum invested.
Write whether the following statement vary directly, vary inversely with each other, or neither of the two.
Increase in cost and number of shirts that can be purchased if the budget remains the same.
Sobi types 108 words in 6 minutes. How many words would she type in half an hour?
If a and b vary inversely to other, then find the values of p, q, r ; x, y, z and l, m, n.
a | 2 | y | 6 | 10 |
b | x | 12.5 | 15 | z |
At a particular time, the length of the shadow of Qutub Minar whose height is 72 m is 80 m. What will be the height of an electric pole, the length of whose shadow at the same time is 1000 cm?