Six men can complete a work in 12 days. Two days later, 6 more men joined them. How many days will they take to complete the remaining work? - Mathematics

Advertisements
Advertisements

Question

Six men can complete a work in 12 days. Two days later, 6 more men joined them. How many days will they take to complete the remaining work?

Sum

Solution

  Number of men No. of days
Initially 6 12
2 days later available work 6 12 − 2 = 10
Remaining work after 6 men joined 6 + 6 = 12  x

As the number of men increases the number of days decreases.

∴ They are inversely proportional

x1y1 = x2y2

6 × 10 = 12 × x

x = `(6 xx 10)/12`

x = 5 days

∴ Remaining work will be complete in 5 days

shaalaa.com
  Is there an error in this question or solution?
Chapter 4: Direct and Inverse Proportion - Exercise 4.3 [Page 81]

APPEARS IN

Samacheer Kalvi Mathematics - Term 1 [English] Class 7 TN Board
Chapter 4 Direct and Inverse Proportion
Exercise 4.3 | Q 13 | Page 81
Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×