Advertisements
Advertisements
Question
A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?
Solution
∵ In 9 months, a part of stadium can complete by 560 persons.
∴ In 1 month, the work can be complete by 9 × 560 = 5040 persons.
∵ In 5 months, the work can be complete by `5040/5` = 1008 persons
Now, number of extra persons required to complete the work in 5 months = 1008 – 560 = 448
APPEARS IN
RELATED QUESTIONS
A batch of bottles was packed in 25 boxes with 12 bottles in each box. If the same batch is packed using 20 bottles in each box, how many boxes would be filled?
In which of the following table x and y vary inversely:
x | 4 | 3 | 6 | 1 |
y | 9 | 12 | 8 | 36 |
In which of the following table x and y vary inversely:
x | 9 | 24 | 15 | 3 |
y | 8 | 3 | 4 | 25 |
It x and y vary inversely, fill in the following blank:
x | 16 | 32 | 8 | 128 |
y | 4 | ... | ... | 0.25 |
A work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men?
If x and y vary inversely as other and x = 30, find y when constant of variation = 900.
Two quantities are said to vary ______ with each other if an increase in one causes a decrease in the other in such a manner that the product of their corresponding values remains constant.
If x varies inversely as y and x = 4 when y = 6, then when x = 3 the value of y is ______.
Write whether the following statement vary directly, vary inversely with each other, or neither of the two.
Increase in cost and number of shirts that can be purchased if the budget remains the same.
If x varies inversely as y and y = 60 when x = 1.5. Find x. when y = 4.5.