Advertisements
Advertisements
प्रश्न
A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?
उत्तर
∵ In 9 months, a part of stadium can complete by 560 persons.
∴ In 1 month, the work can be complete by 9 × 560 = 5040 persons.
∵ In 5 months, the work can be complete by `5040/5` = 1008 persons
Now, number of extra persons required to complete the work in 5 months = 1008 – 560 = 448
APPEARS IN
संबंधित प्रश्न
Find the constant of variation from the table given below:
x | 3 | 5 | 7 | 9 |
y | 12 | 20 | 28 | 36 |
Set up a table and solve the following problems. Use unitary method to verify the answer.
In which of the following table x and y vary inversely:
x | 4 | 3 | 6 | 1 |
y | 9 | 12 | 8 | 36 |
Which of the following quantities vary inversely as other?
Journey (x km) undertaken by a car and the petrol (y litres) consumed by it.
It takes 60 days for 10 machines to dig a hole. Assuming that all machines work at the same speed, how long will it take 30 machines to dig the same hole?
Six men can complete a work in 12 days. Two days later, 6 more men joined them. How many days will they take to complete the remaining work?
If two quantities p and q vary inversely with each other then ______ of their corresponding values remains constant.
If p and q are in inverse variation then (p + 2) and (q – 2) are also in inverse proportion.
Write whether the following statement vary directly, vary inversely with each other, or neither of the two.
The number of people working and the time to complete a given work.
If x varies inversely as y and x = 20 when y = 600, find y when x = 400.
In a hostel of 50 girls, there are food provisions for 40 days. If 30 more girls join the hostel, how long will these provisions last?