हिंदी
तमिलनाडु बोर्ड ऑफ सेकेंडरी एज्युकेशनएसएसएलसी (अंग्रेजी माध्यम) कक्षा ७

Six men can complete a work in 12 days. Two days later, 6 more men joined them. How many days will they take to complete the remaining work? - Mathematics

Advertisements
Advertisements

प्रश्न

Six men can complete a work in 12 days. Two days later, 6 more men joined them. How many days will they take to complete the remaining work?

योग

उत्तर

  Number of men No. of days
Initially 6 12
2 days later available work 6 12 − 2 = 10
Remaining work after 6 men joined 6 + 6 = 12  x

As the number of men increases the number of days decreases.

∴ They are inversely proportional

x1y1 = x2y2

6 × 10 = 12 × x

x = `(6 xx 10)/12`

x = 5 days

∴ Remaining work will be complete in 5 days

shaalaa.com
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 4: Direct and Inverse Proportion - Exercise 4.3 [पृष्ठ ८१]

APPEARS IN

सामाचीर कलवी Mathematics - Term 1 [English] Class 7 TN Board
अध्याय 4 Direct and Inverse Proportion
Exercise 4.3 | Q 13 | पृष्ठ ८१
Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×