प्रश्न

A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?

संक्षेप में उत्तर

उत्तर

Let x be the extra number of men employed to complete the job in 7 months.
 

Number of men 420 x
Months 9 7

\[\text{ Since the number of men hired and the time required to finish the piece of work are in inverse variation, we have } : \]
\[420 \times 9 = 7x\]
\[ \Rightarrow x = \frac{420 \times 9}{7}\]
\[ = 540\]
\[\text{ Thus, the number of extra men required to complete the job in 7 months }  = 540 - 420 = 120\]

shaalaa.com
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Direct and Inverse Variations - Exercise 10.2 [पृष्ठ १३]

APPEARS IN

आरडी शर्मा Mathematics [English] Class 8
अध्याय 10 Direct and Inverse Variations
Exercise 10.2 | Q 7 | पृष्ठ १३

वीडियो ट्यूटोरियलVIEW ALL [1]

Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×