Question

Four new machines M1, M2, M3 and M4 are to be installed in a machine shop. There are five vacant places A, B, C, D and E available. Because of limited space, machine M2 cannot be placed at C and M3 cannot be placed at A. The cost matrix is given below.

Machines Places
  A B C D E
M1 4 6 10 5 6
M2 7 4 5 4
M3 6 9 6 2
M4 9 3 7 2 3

Find the optimal assignment schedule

Chart
Sum

Solution

Step 1:

Here, number of rows and columns are not equal.

∴ The problem is unbalanced.

∴ It is balanced by introducing dummy machine M5 with zero cost.

Also, M2 cannot be placed at C and M3 cannot be placed at A.

Let a very high cost (`oo`) be assigned to corresponding elements.

∴ Matrix obtained is as follows:

Machines Places
  A B C D E
M1 4 6 10 5 6
M2 7 4 `oo` 5 4
M3 `oo` 6 9 6 2
M4 9 3 7 2 3
M5 0 0 0 0 0

Step 2: Row minimum

Subtract the smallest element in each row from every element in its row.

The matrix obtained is given below:

Machines Places
  A B C D E
M1 0 2 6 1 2
M2 3 0 `oo` 1 0
M3 `oo` 4 7 4 0
M4 7 1 5 0 1
M5 0 0 0 0 0

Step 3: Column minimum

Here, each column contains element zero.

∴ Matrix obtained by column minimum is same as the above matrix.

Step 4:

Draw minimum number of vertical and horizontal lines to cover all zeros.

First cover all rows and columns which have maximum number of zeros.

Machines Places
  A B C D E
M1 0 2 6 1 2
M2 3 0 `oo` 1 0
M3 `oo` 4 7 4 0
M4 7 1 5 0 1
M5 0 0 0 0 0

Step 5:

From step 4, minimum number of lines covering all the zeros are 5, which is equal to order of the matrix, i.e., 5.

∴ Select a row with exactly one zero, enclose that zero in () and cross out all zeros in its respective column.

Similarly, examine each row and column and mark the assignment ().

The matrix obtained is as follows:

Machines Places
  A B C D E
M1 0 2 6 1 2
M2 3 0 `oo` 1 0
M3 `oo` 4 7 4 0
M4 7 1 5 0 1
M5 0 0 0 0 0

Step 6:

The matrix obtained in step 5 contains exactly one assignment for each row and column.

∴ Optimal assignment schedule is as follows:

Machines Place Cost
M1 A 4
M2 B 4
M3 E 2
M4 D 2
M5 C 0

∴ The total minimum cost = 4 + 4 + 2 + 2 + 0

= ₹ 12

Note that no machine will be installed at location C, since it gets dummy machine M

shaalaa.com
Special Cases of Assignment Problem
  Is there an error in this question or solution?
Chapter 7: Assignment Problem and Sequencing - Exercise 7.1 [Page 119]

RELATED QUESTIONS

A company has a team of four salesmen and there are four districts where the company wants to start its business. After taking into account the capabilities of salesmen and the nature of districts, the company estimates that the profit per day in rupees for each salesman in each district is as below:

Salesman District
  1 2 3 4
A 16 10 12 11
B 12 13 15 15
C 15 15 11 14
D 13 14 14 15

Find the assignment of salesman to various districts which will yield maximum profit.


In the modification of a plant layout of a factory four new machines M1, M2, M3 and M4 are to be installed in a machine shop. There are five vacant places A, B, C, D and E available. Because of limited space, machine M2 cannot be placed at C and M3 cannot be placed at A. The cost of locating a machine at a place (in hundred rupees) is as follows.

Machines Location
A B C D E
M1 9 11 15 10 11
M2 12 9 10 9
M3 11 14 11 7
M4 14 8 12 7 8

Find the optimal assignment schedule.


Fill in the blank :

When the number of rows is equal to the number of columns then the problem is said to be _______ assignment problem.


Fill in the blank :

If the given matrix is not a _______ matrix, the assignment problem is called an unbalanced problem.


Fill in the blank :

A dummy row(s) or column(s) with the cost elements as _______ is added to the matrix of an unbalanced assignment problem to convert into a square matrix.


Maximization assignment problem is transformed to minimization problem by subtracting each entry in the table from the _______ value in the table.


Fill in the blank :

In an assignment problem, a solution having _______ total cost is an optimum solution.


Fill in the blank :

In maximization type, all the elements in the matrix are subtracted from the _______ element in the matrix.


To convert the assignment problem into a maximization problem, the smallest element in the matrix is deducted from all other elements.


State whether the following is True or False :

The purpose of dummy row or column in an assignment problem is to obtain balance between total number of activities and total number of resources.


State whether the following is True or False

In number of lines (horizontal on vertical) > order of matrix then we get optimal solution.


Solve the following problem :

Solve the following assignment problem to maximize sales:

Salesman Territories
I II III IV V
A 11 16 18 15 15
B 7 19 11 13 17
C 9 6 14 14 7
D 13 12 17 11 13

Solve the following problem :

The estimated sales (tons) per month in four different cities by five different managers are given below:

Manager Cities
P Q R S
I 34 36 33 35
II 33 35 31 33
III 37 39 35 35
IV 36 36 34 34
V 35 36 35 33

Find out the assignment of managers to cities in order to maximize sales.


An unbalanced assignment problems can be balanced by adding dummy rows or columns with ______ cost


State whether the following statement is True or False:

To convert the assignment problem into maximization problem, the smallest element in the matrix is to deducted from all other elements


Find the assignments of salesman to various district which will yield maximum profit

Salesman District
1 2 3 4
A 16 10 12 11
B 12 13 15 15
C 15 15 11 14
D 13 14 14 15

For the following assignment problem minimize total man hours:

Subordinates Required hours for task
I II III IV
A 7 25 26 10
B 12 27 3 25
C 37 18 17 14
D 18 25 23 9

Subtract the `square` element of each `square` from every element of that `square`

Subordinates Required hours for task
I II III IV
A 0 18 19 3
B 9 24 0 22
C 23 4 3 0
D 9 16 14 0

Subtract the smallest element in each column from `square` of that column.

Subordinates Required hours for task
I II III IV
A `square` `square` 19 `square`
B `square` `square` 0 `square`
C `square` `square` 3 `square`
D `square` `square` 14 `square`

The lines covering all zeros is `square` to the order of matrix `square`

The assignment is made as follows:

Subordinates Required hours for task
I II III IV
A 0 14 19 3
B 9 20 0 22
C 23 0 3 0
D 9 12 14 0

Optimum solution is shown as follows:

A → `square, square` → III, C → `square, square` → IV

Minimum hours required is `square` hours


A marketing manager has list of salesmen and territories. Considering the travelling cost of the salesmen and the nature of territory, the marketing manager estimates the total of cost per month (in thousand rupees) for each salesman in each territory. Suppose these amounts are as follows:

Salesman Territories
  I II III IV V
A 11 16 18 15 15
B 7 19 11 13 17
C 9 6 14 14 7
D 13 12 17 11 13

Find the assignment of salesman to territories that will result in minimum cost.


To solve the problem of maximization objective, all the elements in the matrix are subtracted from the largest element in the matrix.


Three new machines M1, M2, M3 are to be installed in a machine shop. There are four vacant places A, B, C, D. Due to limited space, machine M2 can not be placed at B. The cost matrix (in hundred rupees) is as follows:

Machines Places
  A B C D
M1 13 10 12 11
M2 15 - 13 20
M3 5 7 10 6

Determine the optimum assignment schedule and find the minimum cost.