Advertisements
Advertisements
Question
Solve the following problem :
The estimated sales (tons) per month in four different cities by five different managers are given below:
Manager | Cities | |||
P | Q | R | S | |
I | 34 | 36 | 33 | 35 |
II | 33 | 35 | 31 | 33 |
III | 37 | 39 | 35 | 35 |
IV | 36 | 36 | 34 | 34 |
V | 35 | 36 | 35 | 33 |
Find out the assignment of managers to cities in order to maximize sales.
Solution
Step 1:
The given problem is maximization problem. This can be converted to minimization problem by subtracting all the elements from the largest element which is 39.
Also, the number of rows is not equal to number of columns.
∴ It is an unbalanced assignment problem. It can be balanced by introducing a dummy city T with zero sales.
The resulting matrix is
Manager | Cities | ||||
P | Q | R | S | T | |
I | 5 | 3 | 6 | 4 | 0 |
II | 6 | 4 | 8 | 6 | 0 |
III | 2 | 0 | 4 | 4 | 0 |
IV | 3 | 3 | 5 | 5 | 0 |
V | 4 | 3 | 4 | 6 | 0 |
Step 2: Row minimum
Here, each row contains element zero.
∴ Matrix obtained by row minimum is same as above matrix
Step 3: Column minimum
Subtract the smallest element in each column of assignment matrix obtained in step 2 from every element in its column.
Manager | Cities | ||||
P | Q | R | S | T | |
I | 3 | 3 | 2 | 0 | 0 |
II | 4 | 4 | 4 | 2 | 0 |
III | 0 | 0 | 0 | 0 | 0 |
IV | 1 | 3 | 1 | 1 | 0 |
V | 2 | 3 | 0 | 2 | 0 |
Step 4:
Draw minimum number of vertical and horizontal lines to cover all zeros.
First cover all rows and columns which have maximum number of zeros.
Manager | Cities | ||||
P | Q | R | S | T | |
I | 3 | 3 | 2 | 0 | 0 |
II | 4 | 4 | 4 | 2 | 0 |
III | 0 | 0 | 0 | 0 | 0 |
IV | 1 | 3 | 1 | 1 | 0 |
V | 2 | 3 | 0 | 2 | 0 |
Step 5:
From step 4, minimum number of lines covering all the zeros are 4, which is less than order of matrix, i.e., 5.
∴ Select smallest element from all the uncovered elements, i.e., 1 and subtract it from all the uncovered elements and add it to the elements which lie at the intersection of two lines.
Manager | Cities | ||||
P | Q | R | S | T | |
I | 2 | 2 | 2 | 0 | 0 |
II | 3 | 3 | 4 | 2 | 0 |
III | 0 | 0 | 1 | 1 | 1 |
IV | 0 | 2 | 1 | 1 | 0 |
V | 1 | 2 | 0 | 2 | 0 |
Step 6:
Draw minimum number of vertical and horizontal lines to cover all zeros.
Manager | Cities | ||||
P | Q | R | S | T | |
I | 2 | 2 | 2 | 0 | 0 |
II | 3 | 3 | 4 | 2 | 0 |
III | 0 | 0 | 1 | 1 | 1 |
IV | 0 | 2 | 1 | 1 | 0 |
V | 1 | 2 | 0 | 2 | 0 |
Step 7:
From step 6, minimum number of lines covering all the zeros are 5, which is equal to order of the matrix, i.e., 5.
∴ Select a row with exactly one zero, enclose that zero in () and cross out all zeros in its respective column.
Similarly, examine each row and column and mark the assignment ().
∴ The matrix obtained is as follows:
Manager | Cities | ||||
P | Q | R | S | T | |
I | 2 | 2 | 2 | 0 | 0 |
II | 3 | 3 | 4 | 2 | 0 |
III | 0 | 0 | 1 | 1 | 1 |
IV | 0 | 2 | 1 | 1 | 0 |
V | 1 | 2 | 0 | 2 | 0 |
∴ The optimal solution is
Manager | Cities | Sales (tons) |
I | S | 35 |
II | T | 0 |
III | Q | 39 |
IV | P | 36 |
V | R | 35 |
∴ Maximum sales 35 + 0 + 39 + 36 + 35 = 145 tons.
APPEARS IN
RELATED QUESTIONS
Four new machines M1, M2, M3 and M4 are to be installed in a machine shop. There are five vacant places A, B, C, D and E available. Because of limited space, machine M2 cannot be placed at C and M3 cannot be placed at A. The cost matrix is given below.
Machines | Places | ||||
A | B | C | D | E | |
M1 | 4 | 6 | 10 | 5 | 6 |
M2 | 7 | 4 | – | 5 | 4 |
M3 | – | 6 | 9 | 6 | 2 |
M4 | 9 | 3 | 7 | 2 | 3 |
Find the optimal assignment schedule
A company has a team of four salesmen and there are four districts where the company wants to start its business. After taking into account the capabilities of salesmen and the nature of districts, the company estimates that the profit per day in rupees for each salesman in each district is as below:
Salesman | District | |||
1 | 2 | 3 | 4 | |
A | 16 | 10 | 12 | 11 |
B | 12 | 13 | 15 | 15 |
C | 15 | 15 | 11 | 14 |
D | 13 | 14 | 14 | 15 |
Find the assignment of salesman to various districts which will yield maximum profit.
Fill in the blank :
An assignment problem is said to be unbalanced when _______.
Fill in the blank :
When the number of rows is equal to the number of columns then the problem is said to be _______ assignment problem.
Fill in the blank :
If the given matrix is not a _______ matrix, the assignment problem is called an unbalanced problem.
Fill in the blank :
A dummy row(s) or column(s) with the cost elements as _______ is added to the matrix of an unbalanced assignment problem to convert into a square matrix.
Maximization assignment problem is transformed to minimization problem by subtracting each entry in the table from the _______ value in the table.
Fill in the blank :
In an assignment problem, a solution having _______ total cost is an optimum solution.
State whether the following is True or False
In number of lines (horizontal on vertical) > order of matrix then we get optimal solution.
Solve the following problem :
Solve the following assignment problem to maximize sales:
Salesman | Territories | ||||
I | II | III | IV | V | |
A | 11 | 16 | 18 | 15 | 15 |
B | 7 | 19 | 11 | 13 | 17 |
C | 9 | 6 | 14 | 14 | 7 |
D | 13 | 12 | 17 | 11 | 13 |
Choose the correct alternative:
The cost matrix of an unbalanced assignment problem is not a ______
State whether the following statement is True or False:
To convert the assignment problem into maximization problem, the smallest element in the matrix is to deducted from all other elements
Find the assignments of salesman to various district which will yield maximum profit
Salesman | District | |||
1 | 2 | 3 | 4 | |
A | 16 | 10 | 12 | 11 |
B | 12 | 13 | 15 | 15 |
C | 15 | 15 | 11 | 14 |
D | 13 | 14 | 14 | 15 |
For the following assignment problem minimize total man hours:
Subordinates | Required hours for task | |||
I | II | III | IV | |
A | 7 | 25 | 26 | 10 |
B | 12 | 27 | 3 | 25 |
C | 37 | 18 | 17 | 14 |
D | 18 | 25 | 23 | 9 |
Subtract the `square` element of each `square` from every element of that `square`
Subordinates | Required hours for task | |||
I | II | III | IV | |
A | 0 | 18 | 19 | 3 |
B | 9 | 24 | 0 | 22 |
C | 23 | 4 | 3 | 0 |
D | 9 | 16 | 14 | 0 |
Subtract the smallest element in each column from `square` of that column.
Subordinates | Required hours for task | |||
I | II | III | IV | |
A | `square` | `square` | 19 | `square` |
B | `square` | `square` | 0 | `square` |
C | `square` | `square` | 3 | `square` |
D | `square` | `square` | 14 | `square` |
The lines covering all zeros is `square` to the order of matrix `square`
The assignment is made as follows:
Subordinates | Required hours for task | |||
I | II | III | IV | |
A | 0 | 14 | 19 | 3 |
B | 9 | 20 | 0 | 22 |
C | 23 | 0 | 3 | 0 |
D | 9 | 12 | 14 | 0 |
Optimum solution is shown as follows:
A → `square, square` → III, C → `square, square` → IV
Minimum hours required is `square` hours
To solve the problem of maximization objective, all the elements in the matrix are subtracted from the largest element in the matrix.
Three new machines M1, M2, M3 are to be installed in a machine shop. There are four vacant places A, B, C, D. Due to limited space, machine M2 can not be placed at B. The cost matrix (in hundred rupees) is as follows:
Machines | Places | |||
A | B | C | D | |
M1 | 13 | 10 | 12 | 11 |
M2 | 15 | - | 13 | 20 |
M3 | 5 | 7 | 10 | 6 |
Determine the optimum assignment schedule and find the minimum cost.